Bldg-Alter/Repair Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

SUPPLEMENTAL TO PERMIT#10010-10000-02370 TO CHECK REVISED SFD DESIGN A

Inspection Activity
Date: 03/29/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 03/29/2023
Type: Public Counter
Result: Completed
Status: Issued
Date: 03/29/2023
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 05/10/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 05/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 05/16/2023
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 10/18/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 10/19/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 06/02/2023
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 06/02/2023
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 10/26/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/25/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/23/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/07/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 07/17/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 11/13/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 11/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 11/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 11/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/22/2023
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 06/28/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/27/2024
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/28/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 09/20/2023
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 09/20/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 12/12/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 12/18/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/18/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 07/03/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 07/03/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 07/02/2024
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Date: 12/28/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 07/02/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/03/2024
Type: Structural Steel Frame
Result: Insp Cancelled
Status: Issued
Date: 01/10/2024
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 01/17/2024
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 01/31/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/02/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 01/31/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/31/2024
Type: Structural Steel Frame
Result: Corrections Issued
Status: Issued
Date: 02/15/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/16/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/12/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 02/12/2024
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 02/15/2024
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 02/27/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 03/04/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/04/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/08/2024
Type: Deputy Other (see comments)
Result: Conditional Approval
Status: Issued
Date: 03/07/2024
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/10/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/15/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/16/2024
Type: Structural Steel Frame
Result: Insp Cancelled
Status: Issued
Date: 04/16/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 04/16/2024
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 04/15/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/18/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/15/2024
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
LUMAR CORPORATION

License number: 1027838
Type: A
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: BABAK NEHORAY

Type:

Address: 11400 W OLYMPIC BLVD, 9TH-FL, LA, CA

Phone:

Experience: years

Applicant: CYNTHIA .