Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

Inspection Activity
Date: 07/10/2014
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 03/11/2015
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/24/2015
Type: TCO Sprinkler Verification
Result: Completed (special insp)
Status: Issued
Date: 02/24/2015
Type: T-Bar Ceiling
Result: Partial Inspection
Status: Issued
Date: 03/11/2015
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 04/17/2015
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 01/02/2015
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 04/07/2015
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 01/13/2015
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 07/08/2014
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 04/03/2015
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 03/12/2015
Type: SWPPP-Const. Storm Water
Result: Completed
Status: Issued
Date: 03/26/2015
Type: TCO Heat,Vent,A/C Verification
Result: Completed (special insp)
Status: Issued
Date: 03/17/2015
Type: SUSMP-Std. Urban Storm Water
Result: Approved
Status: Issued
Date: 03/23/2015
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/29/2014
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 03/24/2015
Type: TCO Grading Verification
Result: Completed (special insp)
Status: Issued
Date: 03/17/2015
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 03/11/2015
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 07/10/2014
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 03/24/2015
Type: TCO Heat,Vent,A/C Verification
Result: Not Ready for Inspection
Status: Issued
Date: 07/02/2014
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 12/19/2014
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 03/17/2015
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 01/02/2015
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 01/20/2015
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/11/2015
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 03/23/2015
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/20/2015
Type: Green Building Final
Result: No Access for Inspection
Status: Issued
Date: 04/20/2015
Type: Green Building Final
Result: No Access for Inspection
Status: Issued
Date: 07/02/2014
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 03/17/2015
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/24/2015
Type: TCO Electrical Verification
Result: Completed (special insp)
Status: Issued
Date: 03/24/2015
Type: TCO Green Code Verification
Result: Completed (special insp)
Status: Issued
Date: 03/24/2015
Type: TCO Plumbing Verification
Result: Completed (special insp)
Status: Issued
Date: 04/03/2015
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 01/02/2015
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 12/29/2014
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 09/14/2015
Type: Special/Order Compliance
Result: Conditional Approval
Status: Issued
Date: 12/15/2014
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 03/11/2015
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/08/2015
Type: Green Building Final
Result: Partial Approval
Status: Issued
Date: 02/25/2015
Type: T-Bar Ceiling
Result: Partial Inspection
Status: Issued
Date: 12/19/2014
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 03/11/2015
Type: SUSMP-Std. Urban Storm Water
Result: Not Ready for Inspection
Status: Issued
Date: 12/29/2014
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 01/22/2015
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 03/11/2015
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 01/09/2015
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/20/2015
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 03/16/2015
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/12/2017
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 04/13/2017
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 04/12/2017
Type: Plumbing Verification
Result: Insp Scheduled
Status: Issued
Date: 04/12/2017
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 04/12/2017
Type: Green Code Verification
Result: CofO on Hold
Status: Issued
Date: 04/12/2017
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 12/18/2024
Type:
Result:
Status:
Date: 01/24/2018
Type: Grading Verification
Result: OK for CofO
Status: Issued
Date: 01/22/2018
Type: Green Building Final
Result: Approved
Status: Issued
Date: 12/18/2024
Type:
Result:
Status:
Date: 12/18/2024
Type:
Result:
Status:
Date: 12/18/2024
Type:
Result:
Status:
Date: 12/18/2024
Type:
Result:
Status:
Date: 12/18/2024
Type:
Result:
Status:
Date: 12/18/2024
Type:
Result:
Status:
Date: 09/11/2014
Type:
Result:
Status:
Date: 11/10/2014
Type:
Result:
Status:
Date: 09/17/2014
Type:
Result:
Status:
Date: 09/18/2014
Type:
Result:
Status:
Date: 09/19/2014
Type:
Result:
Status:
Date: 07/31/2014
Type:
Result:
Status:
Date: 09/12/2014
Type:
Result:
Status:
Date: 09/15/2014
Type:
Result:
Status:
Date: 09/16/2014
Type:
Result:
Status:
Date: 11/14/2014
Type:
Result:
Status:
Date: 08/27/2014
Type:
Result:
Status:
Date: 12/12/2014
Type:
Result:
Status:
Date: 12/12/2014
Type:
Result:
Status:
Date: 12/12/2014
Type:
Result:
Status:
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
MILLER CONSTRUCTION INC

License number: 347781
Type: B
Phone: Speak with a Permit Expert
Location: HUNTINGTON BEACH, CA

Permit Applicant

Principal: TIMOTHY MILLER

Type:

Address: 1300 BRISTOL ST. N., NEWPORT BEACH, CA

Phone:

Experience: years

Applicant: HANNIBAL PETROSSI