Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

PROPOSED 2-STORY, 9-UNIT APARTMENT BUILDING WITH BASEMENT PARKING GARA

Inspection Activity
Date: 07/26/2016
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 03/04/2016
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 04/01/2016
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 09/24/2015
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 09/24/2015
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 09/02/2015
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 04/01/2016
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/14/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 03/04/2016
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/02/2015
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 12/08/2015
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 12/08/2015
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 04/01/2016
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 11/09/2015
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 03/04/2016
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 10/15/2015
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 02/12/2016
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 02/12/2016
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 10/14/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/07/2015
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 12/11/2015
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 12/07/2015
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 10/28/2015
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 10/14/2015
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 02/12/2016
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 09/24/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 10/28/2015
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 11/20/2015
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 10/28/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 12/11/2015
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 12/07/2015
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 12/11/2015
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 02/04/2016
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 02/12/2016
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 09/02/2015
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 04/28/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/19/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/19/2016
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 05/19/2016
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 06/23/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/23/2016
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 06/23/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/28/2016
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/23/2016
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 06/28/2016
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/11/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 12/05/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 04/24/2017
Type: Final
Result: No Access for Inspection
Status: Issued
Date: 05/05/2017
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: METHANE-Rough
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: METHANE-Final
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Drywall Nailing
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 05/04/2017
Type: SUSMP-Std. Urban Storm Water
Result: Insp Scheduled
Status: Issued
Date: 05/05/2017
Type: Structural Steel Frame
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: SWPPP-Const. Storm Water
Result: Insp Scheduled
Status: Issued
Date: 05/05/2017
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 05/05/2017
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 05/19/2017
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 05/19/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/19/2017
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 06/02/2017
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 05/31/2017
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 06/05/2017
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 06/06/2017
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 06/13/2017
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 06/13/2017
Type: METHANE-Subgrade
Result: Partial Approval
Status: Issued
Date: 06/13/2017
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 10/03/2017
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/26/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/26/2017
Type: Verify Sprinkler Sign Off
Result: Partial Inspection
Status: Issued
Date: 10/26/2017
Type: METHANE-Rough
Result: Approved
Status: Issued
Date: 10/26/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 11/16/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 11/14/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 01/16/2018
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 03/02/2018
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2018
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 02/14/2018
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 02/14/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 02/14/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 03/02/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 03/02/2018
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: SUSMP-Std. Urban Storm Water
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 03/02/2018
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 03/02/2018
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2018
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/08/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 03/22/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/22/2018
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 03/22/2018
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 03/29/2018
Type: Wood Frame
Result: Approved Pending GreenApproval
Status: Issued
Date: 03/29/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 04/06/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 04/06/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 04/10/2018
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 04/10/2018
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 11/14/2018
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 11/14/2018
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 11/13/2018
Type: Final
Result: OK for TCO
Status: Issued
Date: 11/14/2018
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 11/14/2018
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
KINGSTUD CONSTRUCTION INC

License number: 958806
Type: B
Phone: Speak with a Permit Expert
Location: FULLERTON, CA

Permit Applicant

Principal: JONATHAN MATTHEW HANSEN

Type:

Address: 3029 EISENHOWER AVE., ARCADIA, CA

Phone:

Experience: years

Applicant: THANG LE