Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

Inspection Activity
Date: 01/30/2014
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 06/05/2013
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/22/2013
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/15/2014
Type: PLUMBING-Final
Result: Approved
Status: Issued
Date: 11/05/2013
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 06/11/2013
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 06/07/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/11/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 11/21/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/29/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/25/2013
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 09/23/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/21/2013
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 07/15/2014
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 08/23/2013
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/23/2013
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/25/2013
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/16/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/30/2014
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 09/12/2013
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 02/06/2014
Type: Insulation
Result: No Access for Inspection
Status: Issued
Date: 11/21/2013
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/08/2013
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 12/03/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/01/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/30/2013
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/11/2013
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/21/2013
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 12/03/2013
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 05/17/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/04/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/05/2014
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/30/2014
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 11/14/2013
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 09/30/2013
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/25/2013
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 07/16/2014
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/21/2013
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/05/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 02/10/2014
Type: Insulation
Result: Approved
Status: Issued
Date: 07/14/2014
Type: ELECTRICAL-Final
Result: No Access for Inspection
Status: Issued
Date: 12/23/2013
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 11/05/2013
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 08/02/2013
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 12/03/2013
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 07/08/2014
Type: Gas Test
Result: Approved
Status: Issued
Date: 07/29/2013
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 06/12/2013
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 07/10/2014
Type: HVAC-Final
Result: Partial Inspection
Status: Issued
Date: 03/18/2014
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 10/02/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/15/2014
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 04/02/2014
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 05/22/2013
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 11/05/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/23/2013
Type: Underground Mechanical
Result: Partial Inspection
Status: Issued
Date: 04/29/2013
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 11/14/2013
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 07/10/2014
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 02/04/2014
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 07/10/2014
Type: Green Building Final
Result: Conditional Approval
Status: Issued
Date: 01/24/2014
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 06/11/2013
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/04/2013
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 08/16/2013
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 12/23/2013
Type: HVAC-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/22/2013
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 12/03/2013
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/30/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 02/20/2014
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 10/24/2013
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 04/23/2013
Type: Piling/Pier/Caisson
Result: Conditional Approval
Status: Issued
Date: 06/05/2014
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 07/11/2013
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 01/17/2014
Type: HVAC-Rough
Result: Partial Inspection
Status: Issued
Date: 04/16/2014
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 07/12/2013
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 01/30/2014
Type: Green Building Rough
Result: Corrections Issued
Status: Issued
Date: 05/20/2013
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 10/11/2013
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 03/03/2014
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 06/27/2013
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 11/13/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 07/10/2014
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 03/19/2014
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 11/14/2013
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 01/29/2014
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 07/02/2013
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 10/02/2013
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 04/22/2013
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/05/2013
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/04/2013
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 09/23/2013
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/04/2014
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 03/18/2014
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 10/09/2013
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/18/2014
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: Issued
Date: 07/26/2013
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 01/17/2014
Type: ELECTRICAL-Rough
Result: Partial Inspection
Status: Issued
Date: 11/14/2013
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 01/29/2014
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 04/24/2013
Type: Piling/Pier/Caisson
Result: Approved
Status: Issued
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 11/21/2024
Type:
Result:
Status:
Date: 10/07/2014
Type:
Result:
Status:
Date: 08/04/2014
Type:
Result:
Status:
Date: 08/01/2014
Type:
Result:
Status:
Date: 08/04/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Date: 10/07/2014
Type:
Result:
Status:
Date: 08/04/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Date: 08/04/2014
Type:
Result:
Status:
Date: 10/07/2014
Type:
Result:
Status:
Date: 08/05/2014
Type:
Result:
Status:
Date: 07/31/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Date: 07/29/2014
Type:
Result:
Status:
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
TYLER DEVELOPMENT CORPORATION

License number: 451882
Type: B
Phone: Speak with a Permit Expert
Location: CALABASAS, CA

Permit Applicant

Principal: RONALD UDALL

Type:

Address: 4340 CALETA ROAD, AGOURA

Phone:

Experience: years

Applicant: BLYTHE MCKINNEY