Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

RENOVATION AND ADDITION TO EXISTING TYPE VB PROVINCIAL CONVENT AND RE

Inspection Activity
Date: 07/18/2016
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 02/09/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 02/09/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 02/09/2017
Type: Inspection
Result: OK for CofO
Status: CofO Issued
Date: 02/09/2017
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 02/09/2017
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Date: 02/10/2016
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/13/2015
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 10/15/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 12/11/2015
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 12/01/2015
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 12/03/2015
Type: METHANE-Rough
Result: Partial Inspection
Status: Issued
Date: 12/01/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/28/2016
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 01/28/2016
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 12/29/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/03/2015
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 02/29/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 10/15/2015
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 06/12/2015
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 10/20/2015
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/01/2015
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 10/06/2015
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 02/04/2016
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 12/01/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 01/12/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/14/2015
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/01/2015
Type: METHANE-Rough
Result: Partial Inspection
Status: Issued
Date: 02/05/2016
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/03/2015
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 03/01/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/07/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 12/01/2015
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 11/13/2015
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 10/15/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/03/2015
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 12/09/2015
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/25/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 12/11/2015
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/13/2015
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/16/2015
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 02/04/2016
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 12/11/2015
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 04/26/2016
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/26/2016
Type: METHANE-Rough
Result: Insp Cancelled
Status: Issued
Date: 04/26/2016
Type: Green Building Rough
Result: Corrections Issued
Status: Issued
Date: 04/26/2016
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 04/25/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2016
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 05/23/2016
Type: METHANE-Rough
Result: Approved
Status: Issued
Date: 05/23/2016
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 06/06/2016
Type: Insulation
Result: Approved
Status: Issued
Date: 06/06/2016
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 06/24/2016
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 12/12/2016
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 12/16/2016
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 12/13/2016
Type: Green Code Verification
Result: CofO on Hold
Status: Issued
Date: 12/12/2016
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 12/12/2016
Type: Wood Frame
Result: Approved
Status: Issued
Date: 12/12/2016
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/13/2016
Type: Fire Sprinkler Verification
Result: Not Applicable
Status: Issued
Date: 12/12/2016
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 01/04/2017
Type: Green Building Final
Result: Partial Approval
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
CAMBRIDGE HOMES

License number: 736218
Type: B
Phone: Speak with a Permit Expert
Location: MURRIETA, CA

Permit Applicant

Principal: MICHELE DENISE DOLLARHIDE

Type:

Address: 1044 N 114TH ST, OMAHA, NE

Phone:

Experience: years

Applicant: NICHOLE SCHULTES