Bldg-New Permit

PCIS Permit#: 14010-10000-03189

Address: 2265 FAIR PARK, Los Angeles, 90041

Status: CofO Issued

Status Date: 08/19/2017

Tract: TR 237

Property Identifier: Block: , Lot: 80, Zone: RD1.5-1

Assessor Information: Book: 5686, Page: 21, Parcel: 26

Census Tract: 1814

Work Description

Small lot subdivision pursuant to Tentative Tract Map No. VTT-72735. A

Inspection Activity
Date: 02/10/2017
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 09/29/2015
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 09/29/2015
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/17/2016
Type: HVAC-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/27/2015
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 01/25/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/12/2015
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/17/2016
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 10/23/2015
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 10/23/2015
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/27/2015
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/25/2016
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 10/27/2015
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 01/28/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/24/2016
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 11/10/2015
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 10/30/2015
Type: PLUMBING-Rough
Result: Partial Inspection
Status: Issued
Date: 09/29/2015
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 09/18/2015
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 01/28/2016
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 09/29/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/29/2015
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 01/13/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 03/16/2016
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/23/2015
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 12/04/2015
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/24/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 03/15/2016
Type: Shower Pan
Result: Partial Approval
Status: Issued
Date: 09/28/2015
Type: METHANE-Subgrade
Result: Cancelled
Status: Issued
Date: 09/28/2015
Type: METHANE-Barrier
Result: Cancelled
Status: Issued
Date: 09/28/2015
Type: PLUMBING-Rough
Result: Cancelled
Status: Issued
Date: 12/16/2015
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/01/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 09/28/2015
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 10/14/2015
Type: METHANE-Rough
Result: Partial Approval
Status: Issued
Date: 01/15/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 12/16/2015
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/20/2016
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 04/22/2016
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/20/2016
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 04/22/2016
Type: METHANE-Rough
Result: Approved
Status: Issued
Date: 04/22/2016
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 04/22/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/27/2016
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 05/04/2016
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 05/02/2016
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 05/05/2016
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 05/03/2016
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2016
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 05/24/2016
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 11/03/2016
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 11/03/2016
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 11/18/2016
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/18/2016
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 11/18/2016
Type: Smoke Detectors
Result: No Access for Inspection
Status: Issued
Date: 11/18/2016
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 11/18/2016
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 11/18/2016
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/29/2016
Type: Gas Test
Result: Insp Scheduled
Status: Issued
Date: 12/02/2016
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/02/2016
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 12/02/2016
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/16/2016
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 12/20/2016
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 12/20/2016
Type: PLUMBING-Final
Result: Approved
Status: Issued
Date: 12/20/2016
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 12/20/2016
Type: Service/Power Release
Result: Partial Inspection
Status: Issued
Date: 12/23/2016
Type: Grading Verification
Result: OK for CofO
Status: Issued
Date: 01/06/2017
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 01/05/2017
Type: Service/Power Release
Result: Insp Scheduled
Status: Issued
Date: 01/05/2017
Type: Green Building Final
Result: Approved
Status: Issued
Date: 01/05/2017
Type: Final
Result: Partial Approval
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
HEYDAY DEVELOPMENT CORPORATION

License number: 824034
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: BENJAMIN HARDY WRONSKE
Type:
Address: 1313 PALMETTO ST, LOS ANGELES, CA
Phone:
Experience: years
Applicant: KEVIN WRONSKE