Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW 2-STORY 74'4" X 31'2" SFD/ GAR

Inspection Activity
Date: 04/04/2017
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 12/08/2015
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 12/03/2015
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 12/03/2015
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/30/2015
Type: Excavation/Setback/Form/Re-Bar
Result: No Access for Inspection
Status: Issued
Date: 12/29/2015
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 04/11/2017
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/11/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/10/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 04/10/2017
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/07/2017
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 10/10/2017
Type: Shower Pan
Result: Approved
Status: Issued
Date: 10/13/2017
Type: Special/Order Compliance
Result: Insp Cancelled
Status: Issued
Date: 10/12/2017
Type: Special/Order Compliance
Result: Order to Comply Issued
Status: Issued
Date: 10/10/2017
Type: HVAC-Rough
Result: Corrections Issued
Status: Issued
Date: 10/14/2017
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 10/17/2017
Type: Interior/Exterior Lathing
Result: Partial Inspection
Status: Issued
Date: 10/19/2017
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 10/19/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 10/19/2017
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 10/17/2017
Type: HVAC-Rough
Result: Partial Inspection
Status: Issued
Date: 10/24/2017
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 10/24/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 11/01/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 10/30/2017
Type: Insulation
Result: Approved
Status: Issued
Date: 11/14/2017
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 11/14/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 11/14/2017
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 05/22/2018
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 05/22/2018
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 05/22/2018
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 05/22/2018
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 05/22/2018
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 06/02/2018
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 06/15/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 06/15/2018
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 06/15/2018
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 06/15/2018
Type: PLUMBING-Final
Result: Approved
Status: Issued
Date: 06/15/2018
Type: Final
Result: Conditional Approval
Status: Issued
Date: 06/15/2018
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 06/15/2018
Type: Green Building Final
Result: Approved
Status: Issued
Date: 06/15/2018
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 03/01/2018
Type: PLUMBING-Final
Result: Corrections Issued
Status: Issued
Date: 02/26/2018
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 03/01/2018
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 02/26/2018
Type: PLUMBING-Rough
Result: Partial Inspection
Status: Issued
Date: 02/27/2018
Type: Gas Test
Result: Insp Cancelled
Status: Issued
Date: 03/01/2018
Type: Gas Test
Result: Approved
Status: Issued
Date: 02/26/2018
Type: ELECTRICAL-Final
Result: Partial Inspection
Status: Issued
Date: 02/27/2018
Type: ELECTRICAL-Final
Result: Insp Cancelled
Status: Issued
Date: 06/18/2018
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 03/08/2018
Type: Underground Mechanical
Result: Corrections Issued
Status: Issued
Date: 03/08/2018
Type: Gas Test
Result: Partial Inspection
Status: Issued
Date: 03/12/2018
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 03/12/2018
Type: Gas Test
Result: Partial Approval
Status: Issued
Date: 03/21/2018
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 03/22/2018
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 03/22/2018
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 03/23/2018
Type: PLUMBING-Final
Result: Insp Cancelled
Status: Issued
Date: 03/23/2018
Type: ELECTRICAL-Final
Result: Insp Cancelled
Status: Issued
Date: 03/21/2018
Type: ELECTRICAL-Final
Result: Partial Inspection
Status: Issued
Date: 03/27/2018
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 03/27/2018
Type: ELECTRICAL-Final
Result: Partial Inspection
Status: Issued
Date: 03/27/2018
Type: Service/Power Release
Result: Approved
Status: Issued
Date: 07/03/2018
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 07/19/2018
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 07/19/2018
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 07/28/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 07/28/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 07/28/2018
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
ARAM CONSTRUCTION COMPANY

License number: 934479
Type: B
Phone: Speak with a Permit Expert
Location: BEVERLY HILLS, CA

Permit Applicant

Principal: MARYAM KAMRANI

Type:

Address: 636 N HARPER AV, L A

Phone:

Experience: years

Applicant: B SHULMAN