Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

(N) 3 STORY SFD W/ BASEMENT AND GARAGE. NFPA13D

Inspection Activity
Date: 07/19/2016
Type: Deputy Reinf. Concrete
Result: No Access for Inspection
Status: Issued
Date: 07/27/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/28/2016
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 08/03/2016
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 08/05/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 11/09/2015
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/14/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/14/2016
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 12/11/2015
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 11/30/2015
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 11/09/2015
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 01/13/2016
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 07/31/2015
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 03/24/2016
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 03/23/2016
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 11/03/2015
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 11/02/2015
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 04/07/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/10/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/14/2016
Type: Underground Mechanical
Result: Corrections Issued
Status: Issued
Date: 06/15/2016
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 06/29/2016
Type: Deputy Reinf. Concrete
Result: No Access for Inspection
Status: Issued
Date: 06/29/2016
Type: Deputy Reinf. Concrete
Result: No Access for Inspection
Status: Issued
Date: 07/05/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/28/2016
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/28/2016
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/28/2016
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 11/10/2016
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 12/08/2016
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 12/08/2016
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/08/2016
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 12/12/2016
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 12/12/2016
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 12/19/2016
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 12/21/2016
Type: Insulation
Result: Approved
Status: Issued
Date: 12/19/2016
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 12/19/2016
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 12/21/2016
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 12/21/2016
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 12/20/2016
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 12/29/2016
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 12/28/2016
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 01/04/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 01/03/2017
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 04/21/2017
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: Issued
Date: 04/19/2017
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 04/26/2017
Type: Final
Result: Corrections Issued
Status: Issued
Date: 04/24/2017
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/28/2017
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: Issued
Date: 04/24/2017
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/28/2017
Type: Enclosure/Fence
Result: Insp Scheduled
Status: Issued
Date: 05/15/2017
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 05/19/2017
Type: Service/Power Release
Result: Insp Scheduled
Status: Issued
Date: 05/17/2017
Type: Final
Result: Corrections Issued
Status: Issued
Date: 05/15/2017
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/19/2017
Type: Sewer
Result: Insp Scheduled
Status: Issued
Date: 05/17/2017
Type: Green Building Final
Result: Approved
Status: Issued
Date: 05/15/2017
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2017
Type: HVAC-Final
Result: Insp Scheduled
Status: Issued
Date: 05/17/2017
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 05/17/2017
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 05/15/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 05/19/2017
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 05/18/2017
Type: Elevator Verification
Result: Not Applicable
Status: Issued
Date: 05/15/2017
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/17/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 05/16/2017
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 05/15/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/24/2017
Type: Service/Power Release
Result: Approved
Status: CofO in Progress
Date: 05/25/2017
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 05/24/2017
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 06/02/2017
Type: Service/Power Release
Result: Approved
Status: CofO in Progress
Date: 06/02/2017
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: CofO in Progress
Date: 06/15/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 06/15/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 06/15/2017
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
WESTERN BUILT CONSTRUCTION INC

License number: 951783
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: JUSTIN TREVOR KLENTNER

Type:

Address: 18321 VENTURA BL, #615, TARZANA, CA

Phone:

Experience: years

Applicant: MARK SMITH