Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW 4-STORY (3-story above 1-story street level parking garage), 29 UN

Inspection Activity
Date: 08/05/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 02/06/2017
Type: Insulation
Result: Conditional Approval
Status: Issued
Date: 02/14/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/14/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/14/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/14/2017
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 04/03/2017
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 04/03/2017
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 04/05/2017
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 04/27/2016
Type: Pre-Inspection
Result: Cancelled
Status: Issued
Date: 04/29/2016
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 05/05/2016
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 05/13/2016
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 05/13/2016
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 05/13/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/20/2016
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 05/20/2016
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/19/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/16/2016
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 05/27/2016
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/25/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/27/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/27/2016
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 06/02/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/31/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/09/2016
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 06/06/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/09/2016
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 06/06/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/10/2016
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 06/14/2016
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 06/27/2016
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 06/29/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 06/27/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/27/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/27/2016
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 07/01/2016
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 06/29/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 07/01/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/27/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/01/2016
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 06/27/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 07/11/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/11/2016
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 07/11/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/04/2016
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 11/04/2016
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 11/04/2016
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 12/20/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 12/30/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 04/18/2017
Type: Insulation
Result: Conditional Approval
Status: Issued
Date: 04/18/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/18/2017
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/26/2017
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 04/26/2017
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/26/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/04/2017
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/02/2017
Type: Insulation
Result: Conditional Approval
Status: Issued
Date: 05/04/2017
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/04/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 05/02/2017
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 05/04/2017
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/04/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 05/09/2017
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 05/12/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/09/2017
Type: Masonry Wall/Backfill
Result: Conditional Approval
Status: Issued
Date: 05/09/2017
Type: Verify Sprinkler Sign Off
Result: Partial Approval
Status: Issued
Date: 05/09/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/09/2017
Type: Drywall Nailing
Result: Conditional Approval
Status: Issued
Date: 05/09/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 05/09/2017
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 05/18/2017
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/18/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/18/2017
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 05/25/2017
Type: Green Building Rough
Result: No Access for Inspection
Status: Issued
Date: 05/25/2017
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/02/2017
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 06/02/2017
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 06/09/2017
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 06/09/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 06/07/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 06/15/2017
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/15/2017
Type: Green Building Rough
Result: Corrections Issued
Status: Issued
Date: 06/15/2017
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/10/2017
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 10/10/2017
Type: Light Gage Steel Frame
Result: Conditional Approval
Status: Issued
Date: 10/10/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/10/2017
Type: Light Gage Steel Frame
Result: Partial Inspection
Status: Issued
Date: 10/13/2017
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/13/2017
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 10/31/2017
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/31/2017
Type: Green Building Rough
Result: Conditional Approval
Status: Issued
Date: 12/08/2017
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 12/08/2017
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 02/14/2018
Type: Smoke Detectors
Result: Partial Inspection
Status: Issued
Date: 02/14/2018
Type: Green Building Final
Result: Partial Inspection
Status: Issued
Date: 02/14/2018
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 02/14/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 02/14/2018
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 02/14/2018
Type: Final
Result: Partial Inspection
Status: Issued
Date: 02/14/2018
Type: Verify Sprinkler Sign Off
Result: Partial Approval
Status: Issued
Date: 02/14/2018
Type: Reinforced Masonry Frame
Result: Conditional Approval
Status: Issued
Date: 02/14/2018
Type: Reinforced Concrete Frame
Result: Conditional Approval
Status: Issued
Date: 02/23/2018
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 02/26/2018
Type: METHANE-Final
Result: Insp Cancelled
Status: Issued
Date: 03/06/2018
Type: Final
Result: Partial Inspection
Status: Issued
Date: 03/06/2018
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Green Building Final
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Wood Frame
Result: Approved
Status: Issued
Date: 03/06/2018
Type: Structural Steel Frame
Result: Approved
Status: Issued
Date: 03/12/2018
Type: Elevator Verification
Result: OK for CofO
Status: Issued
Date: 08/17/2018
Type: TCO Heat,Vent,A/C Verification
Result: Completed (special insp)
Status: Issued
Date: 08/20/2018
Type: TCO Plumbing Verification
Result: Completed (special insp)
Status: Issued
Date: 08/28/2018
Type: Special/Order Compliance
Result: Insp Scheduled
Status: CofO in Progress
Date: 08/31/2018
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 08/31/2018
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 09/04/2018
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 09/04/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/04/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
TALTECH CONSTRUCTION INC

License number: 885187
Type: B
Phone: Speak with a Permit Expert
Location: GLENDALE, CA

Permit Applicant

Principal: GARNIK GHOLIKANDI BADALYANS

Type:

Address: 21731 AMBAR DR., WOODLAND HILLS, CA

Phone:

Experience: years

Applicant: KAMRAN