Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW TWO-STORY COMMERCIAL 2-TENANT BUILDING

Inspection Activity
Date: 11/01/2017
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 11/02/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/16/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/19/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 04/19/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 05/03/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 11/22/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 04/30/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/02/2018
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/04/2018
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/01/2018
Type: Masonry Wall/Backfill
Result: Conditional Approval
Status: Issued
Date: 05/01/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 11/27/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/29/2017
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 11/29/2017
Type: Special/Order Compliance
Result: Not Ready for Inspection
Status: Issued
Date: 12/06/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/04/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 12/08/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/11/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/13/2017
Type: Public Counter
Result: Completed
Status: Issued
Date: 12/12/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/13/2017
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 12/13/2017
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 12/19/2017
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 05/25/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 01/05/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 01/16/2018
Type: Masonry Wall/Backfill
Result: Corrections Issued
Status: Issued
Date: 01/19/2018
Type: Wall Anchors
Result: Insp Scheduled
Status: Issued
Date: 01/17/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 01/19/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 01/22/2018
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 02/07/2018
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 06/11/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 10/29/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 06/18/2018
Type: Pre-Inspection
Result: No Access for Inspection
Status: Issued
Date: 06/21/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 06/29/2018
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 06/28/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/25/2018
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 03/19/2018
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 03/21/2018
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 03/29/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/03/2018
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 07/02/2018
Type: Masonry Wall/Backfill
Result: Cancelled
Status: Issued
Date: 04/02/2018
Type: Masonry Wall/Backfill
Result: Corrections Issued
Status: Issued
Date: 04/12/2018
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/12/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 04/12/2018
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/12/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/16/2018
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 07/19/2018
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 07/11/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 07/09/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 07/31/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 08/01/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 08/07/2018
Type: Masonry Wall/Backfill
Result: Approved
Status: Issued
Date: 08/15/2018
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 08/17/2018
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 08/20/2018
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/21/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 09/05/2018
Type: Pre-Inspection
Result: Corrections Issued
Status: Issued
Date: 09/18/2018
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 11/15/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 11/13/2019
Type: Insulation
Result: Approved
Status: Issued
Date: 08/07/2019
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 09/28/2018
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 11/13/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 11/22/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 11/25/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 10/03/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/10/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/15/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 10/15/2019
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 04/22/2019
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2019
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 05/08/2019
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 05/14/2019
Type: Pre-Inspection
Result: Corrections Issued
Status: Issued
Date: 01/14/2020
Type: Drywall Nailing
Result: Corrections Issued
Status: Issued
Date: 01/28/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/01/2021
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 02/01/2021
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 02/01/2021
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 02/01/2021
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 12/09/2020
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 06/30/2021
Type: Elevator Verification
Result: CofO on Hold
Status: Issued
Date: 12/20/2022
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 12/23/2022
Type: Elevator Verification
Result: Insp Scheduled
Status: Issued
Date: 12/27/2022
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 06/05/2023
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 03/29/2024
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 03/29/2024
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 03/29/2024
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 04/10/2024
Type: Grading Verification
Result: OK for CofO
Status: CofO in Progress
Date: 04/08/2024
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 04/09/2024
Type: Final
Result: Not Ready for Inspection
Status: CofO in Progress
Date: 04/12/2024
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 04/23/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/23/2024
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 04/23/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
ORSINI CONSTRUCTION INC

License number: 952240
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: KAMRAN ZARGARI

Type:

Address: 6404 WILSHIRE BLVD, 1235, LOS ANGELES, CA

Phone:

Experience: years

Applicant: STEVIE BRUMMER