Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

New 3 story single family dwelling with attached 2-car garage LOT A:

Inspection Activity
Date: 11/04/2016
Type: Pre-Inspection
Result: Corrections Issued
Status: Issued
Date: 11/05/2016
Type: Public Counter
Result: Completed
Status: Issued
Date: 11/04/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/05/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Pending Review
Status: Issued
Date: 11/16/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/16/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/16/2016
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 12/08/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 12/05/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/08/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 12/08/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/13/2016
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/15/2016
Type: Verify Sprinkler Sign Off
Result: Cancelled
Status: Issued
Date: 12/15/2016
Type: Wood Frame
Result: Cancelled
Status: Issued
Date: 12/15/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 12/13/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 12/13/2016
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 04/18/2017
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 04/17/2017
Type: Insulation
Result: Approved
Status: Issued
Date: 04/25/2017
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/27/2017
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 04/25/2017
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/18/2017
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 05/16/2017
Type: Interior/Exterior Lathing
Result: Corrections Issued
Status: Issued
Date: 10/03/2017
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2017
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 10/03/2017
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2017
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/25/2018
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 01/25/2018
Type: Elevator Verification
Result: Not Applicable
Status: Issued
Date: 07/25/2018
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 07/25/2018
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 07/25/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 07/25/2018
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 07/25/2018
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 07/25/2018
Type: Drywall Nailing
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: Drywall Nailing
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 08/08/2018
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 08/08/2018
Type: Drywall Nailing
Result: Insp Cancelled
Status: Issued
Date: 08/06/2018
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 08/08/2018
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 08/08/2018
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 08/08/2018
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 08/08/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 08/07/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 08/21/2018
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/21/2018
Type: Drywall Nailing
Result: No Access for Inspection
Status: Issued
Date: 08/21/2018
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/21/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 08/21/2018
Type: Smoke Detectors
Result: Conditional Approval
Status: Issued
Date: 08/21/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/27/2018
Type: Green Building Rough
Result: Approved
Status: CofO in Progress
Date: 08/27/2018
Type: Smoke Detectors
Result: Partial Inspection
Status: CofO in Progress
Date: 08/27/2018
Type: Final
Result: Not Ready for Inspection
Status: CofO in Progress
Date: 08/29/2018
Type: Green Building Rough
Result: Approved
Status: CofO in Progress
Date: 08/29/2018
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 08/29/2018
Type: Smoke Detectors
Result: Approved
Status: CofO in Progress
Date: 08/27/2018
Type: Drywall Nailing
Result: Partial Inspection
Status: CofO in Progress
Date: 08/27/2018
Type: Green Building Final
Result: Approved
Status: CofO in Progress
Date: 08/29/2018
Type: Drywall Nailing
Result: Approved
Status: CofO in Progress
Date: 08/27/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: CofO in Progress
Date: 08/30/2018
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 09/12/2018
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 09/12/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/12/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
V V DEVELOPMENT CO

License number: 515015
Type: B
Phone: Speak with a Permit Expert
Location: LA CANADA FLINTRIDGE, CA

Permit Applicant

Principal: WON SIK KIM

Type:

Address: 2627 30TH, SANTA MONICA, CA

Phone:

Experience: years

Applicant: KYLE MOSS