Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW 5-STORY APARTMENTS 61 UNITS/OVER 2-BASEMENT LEVEL PARKING GARAGE,

Inspection Activity
Date: 10/10/2017
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 04/16/2018
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 05/28/2019
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/29/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 05/04/2018
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/01/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/01/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 05/01/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/03/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/03/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/04/2018
Type: Deputy Other (see comments)
Result: Conditional Approval
Status: Issued
Date: 06/13/2019
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 06/12/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/18/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 05/18/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 05/18/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/18/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 05/25/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/23/2018
Type: Deputy Other (see comments)
Result: Approved
Status: Issued
Date: 05/23/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 05/22/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 05/22/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/21/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 05/21/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/25/2019
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 05/29/2018
Type: Deputy Other (see comments)
Result: Approved
Status: Issued
Date: 05/29/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 01/26/2018
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 01/31/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 01/29/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 02/06/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 02/05/2018
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 02/13/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/11/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/20/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 02/20/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 02/23/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Deputy Other (see comments)
Result: Insp Scheduled
Status: Issued
Date: 02/20/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/13/2019
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 06/12/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/21/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/18/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 06/19/2018
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/18/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/20/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 03/13/2018
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 03/29/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/01/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 04/09/2018
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 04/09/2018
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 07/16/2018
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 07/19/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/19/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/16/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/08/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 08/09/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/09/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/08/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/07/2018
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 08/08/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 08/21/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 07/25/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 09/05/2018
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 08/01/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 09/26/2018
Type: Deputy Wood Construction
Result: Approved
Status: Issued
Date: 09/24/2018
Type: Deputy Wood Construction
Result: Approved
Status: Issued
Date: 09/26/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 09/28/2018
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/09/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/19/2018
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/16/2018
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 10/19/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/05/2018
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 12/28/2018
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 01/07/2019
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 01/08/2019
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 01/08/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 01/07/2019
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 01/11/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/11/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 01/07/2019
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 01/07/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 01/18/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 01/14/2019
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 01/24/2019
Type: Insulation
Result: No Access for Inspection
Status: Issued
Date: 01/25/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 01/24/2019
Type: Wood Frame
Result: No Access for Inspection
Status: Issued
Date: 01/25/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 04/17/2020
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 01/30/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 02/11/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 02/14/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 02/12/2019
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 02/15/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 02/20/2019
Type: Insulation
Result: Conditional Approval
Status: Issued
Date: 02/20/2019
Type: Drywall Nailing
Result: Conditional Approval
Status: Issued
Date: 02/26/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 09/26/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 03/04/2019
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 03/05/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 03/04/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 03/05/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 03/04/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 03/14/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 03/15/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 03/14/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 03/20/2019
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 03/20/2019
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/21/2019
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/22/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 03/21/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 03/30/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 03/30/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 03/29/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 03/29/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 04/12/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 04/09/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 04/16/2019
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 04/16/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/17/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 04/25/2019
Type: Drywall Nailing
Result: Cancelled
Status: Issued
Date: 04/26/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 04/27/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 05/03/2019
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 05/07/2019
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 05/14/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/13/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 05/14/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 03/03/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/12/2020
Type: Pre-Inspection
Result: Cancelled
Status: Issued
Date: 03/20/2020
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 10/13/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 10/15/2020
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 10/13/2020
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/14/2020
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 10/16/2020
Type: Pressure Vessel Verification
Result: OK for CofO
Status: Issued
Date: 10/15/2020
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 10/13/2020
Type: Reinforced Masonry Frame
Result: Partial Inspection
Status: Issued
Date: 10/15/2020
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 10/15/2020
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 10/13/2020
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 10/13/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/13/2020
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 10/13/2020
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 10/15/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 10/15/2020
Type: Green Building Final
Result: Approved
Status: Issued
Date: 10/13/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 10/15/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 10/15/2020
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 10/13/2020
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 10/22/2020
Type: Elevator Verification
Result: OK for CofO
Status: Issued
Date: 10/21/2020
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 10/21/2020
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 10/22/2020
Type: Final
Result: OK for TCO
Status: Issued
Date: 03/04/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/04/2021
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 03/04/2021
Type: Inspection
Result: OK for CofO
Status: CofO in Progress
Date: 03/04/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/22/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 03/22/2021
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 03/22/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
RAEEN B CONSTRUCTION INC

License number: 465214
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: BAHRAM RAEEN

Type:

Address: 11040 SANTA MONICA BLVD, 326, LA, CA

Phone:

Experience: years

Applicant: MASHA MASHA