Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW DUPLEX WITH ATTACHED 4 CAR CARPORT.

Inspection Activity
Date: 05/17/2016
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 10/02/2017
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 10/03/2017
Type: PLUMBING-Rough
Result: Cancelled
Status: Issued
Date: 10/12/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/17/2018
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 04/17/2018
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 04/17/2018
Type: BUILDING-Rough-Frame
Result: Insp Cancelled
Status: Issued
Date: 11/21/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 11/27/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 05/22/2018
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 03/26/2020
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 06/01/2018
Type: Sewer
Result: Insp Scheduled
Status: Issued
Date: 03/25/2020
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 06/14/2018
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 06/15/2018
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 06/15/2018
Type: Verify Sprinkler Sign Off
Result: Not Required
Status: Issued
Date: 06/15/2018
Type: ELECTRICAL-Rough
Result: Corrections Issued
Status: Issued
Date: 06/14/2018
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 06/14/2018
Type: Service/Power Release
Result: Insp Cancelled
Status: Issued
Date: 06/15/2018
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/15/2018
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 06/14/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 06/15/2018
Type: Green Building Rough
Result: Corrections Issued
Status: Issued
Date: 02/14/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/13/2018
Type: Shower Pan
Result: Partial Approval
Status: Issued
Date: 06/14/2018
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 06/26/2018
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 03/12/2018
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 06/26/2018
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 10/28/2019
Type: Service/Power Release
Result: Approved
Status: Issued
Date: 07/05/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/05/2018
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/05/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/05/2018
Type: Verify Sprinkler Sign Off
Result: No Access for Inspection
Status: Issued
Date: 04/05/2018
Type: Green Building Rough
Result: No Access for Inspection
Status: Issued
Date: 04/05/2018
Type: BUILDING-Rough-Frame
Result: No Access for Inspection
Status: Issued
Date: 07/09/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/09/2018
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 07/09/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 08/02/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 08/02/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 08/10/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 08/10/2018
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 08/21/2018
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 09/25/2018
Type: Interior/Exterior Lathing
Result: Corrections Issued
Status: Issued
Date: 10/02/2018
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2018
Type: Public Counter
Result: Completed
Status: Issued
Date: 10/11/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 10/11/2018
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 10/15/2018
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/15/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/19/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 08/21/2019
Type: Service/Power Release
Result: Corrections Issued
Status: Issued
Date: 09/03/2019
Type: Service/Power Release
Result: Approved
Status: Issued
Date: 04/15/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/15/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/15/2020
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 02/12/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/05/2019
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 12/12/2019
Type: PLUMBING-Final
Result: Insp Scheduled
Status: Issued
Date: 10/08/2019
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/16/2019
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 12/18/2019
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 12/18/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 12/17/2019
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 12/18/2019
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/18/2019
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 12/18/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/18/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 01/09/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/27/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 01/27/2020
Type: Green Building Final
Result: Approved
Status: Issued
Date: 01/27/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 02/19/2020
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
R A M DEVELOPMENT & CONSTRUCTION COMPANY INC

License number: 878197
Type: B
Phone: Speak with a Permit Expert
Location: PALM DESERT, CA

Permit Applicant

Principal: MICHAEL MALLORY ROBINSON

Type:

Address:

Phone:

Experience: years

Applicant: LAURENCE TIGHE