Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

new single family dwelling w/ basement and attached garage

Inspection Activity
Date: 07/26/2016
Type: Grading Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 07/26/2016
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/05/2016
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 08/05/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 08/05/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/03/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 08/03/2016
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 02/09/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/23/2016
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/13/2016
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/26/2016
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/10/2016
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 06/09/2016
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 06/16/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/13/2016
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/14/2016
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/13/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/16/2016
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 06/17/2016
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/16/2016
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 06/13/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/13/2016
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/16/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/16/2016
Type: Structural Steel Frame
Result: Partial Inspection
Status: Issued
Date: 07/06/2016
Type: Reinforced Concrete Frame
Result: Corrections Issued
Status: Issued
Date: 07/14/2016
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 10/24/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 10/24/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 10/24/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2016
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 11/04/2016
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 11/04/2016
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 11/09/2016
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 11/23/2016
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 11/22/2016
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 11/23/2016
Type: Green Building Rough
Result: Corrections Issued
Status: Issued
Date: 11/23/2016
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/23/2016
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 11/30/2016
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 11/30/2016
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 11/30/2016
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 12/02/2016
Type: Insulation
Result: Approved
Status: Issued
Date: 12/19/2016
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 12/19/2016
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 05/31/2017
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 05/31/2017
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 10/11/2017
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 10/11/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 10/11/2017
Type: Final
Result: Conditional Approval
Status: Issued
Date: 10/11/2017
Type: Green Building Final
Result: Approved
Status: Issued
Date: 10/11/2017
Type: Structural Steel Frame
Result: Approved
Status: Issued
Date: 10/11/2017
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 01/10/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/10/2018
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/09/2018
Type: Final
Result: OK to Issue CofO
Status: CofO Issued
Date: 01/10/2018
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 01/10/2018
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Date: 01/09/2018
Type: Grading Verification
Result: OK for CofO
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
DEL CONSTRUCTION

License number: 259218
Type: B
Phone: Speak with a Permit Expert
Location: LANCASTER, CA

Permit Applicant

Principal: LOUIS L FORTE

Type:

Address:

Phone:

Experience: years

Applicant: BIJAN AZADI