Bldg-New Permit

PCIS Permit#: 16010-20000-01046

Address: 857 HAYWORTH, Los Angeles, 90046

Status: CofO Issued

Status Date: 08/01/2022

Tract: TR 4891

Property Identifier: Block: , Lot: 70, Zone: R3-1

Assessor Information: Book: 5529, Page: 21, Parcel: 47

Census Tract: 1944.01

Work Description

APARTMENT HOUSE OVER ONE LEVEL OF BASEMENT GARAGE. 1ST FLOOR PARTIAL G

Inspection Activity
Date: 05/30/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/30/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 05/30/2019
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/30/2019
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 05/15/2018
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 08/10/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 08/10/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/13/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 08/30/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 08/30/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/04/2018
Type: Excavation/Setback/Form/Re-Bar
Result: No Access for Inspection
Status: Issued
Date: 09/06/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/11/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/21/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/21/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 09/21/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 09/27/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/27/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 09/27/2018
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/04/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/04/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 10/01/2018
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/01/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/04/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/01/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/10/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 10/10/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/10/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/18/2018
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 10/19/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 10/19/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 10/22/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/22/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/26/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 10/26/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 10/22/2018
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/22/2018
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2018
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 10/26/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 10/24/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 10/24/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/13/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 11/16/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 11/16/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 11/13/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/13/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 12/29/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 12/29/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Off-Hour Fees Due
Status: Issued
Date: 08/26/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 08/24/2020
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 09/26/2019
Type: Reinforced Concrete Frame
Result: Conditional Approval
Status: Issued
Date: 09/25/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 09/26/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/15/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 03/12/2019
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/15/2019
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 03/12/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/27/2019
Type: Reinforced Masonry Frame
Result: Conditional Approval
Status: Issued
Date: 03/27/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 04/10/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/18/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 04/15/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/15/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 04/18/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/21/2019
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/21/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 09/09/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/26/2020
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/26/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/11/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/11/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 06/16/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/08/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/08/2020
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/14/2020
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 07/16/2020
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 07/24/2020
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 07/24/2020
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/24/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 07/24/2020
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 09/30/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/29/2020
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 07/29/2020
Type: Insulation
Result: Approved
Status: Issued
Date: 09/30/2020
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 09/30/2020
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 01/20/2021
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 01/20/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/20/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 01/20/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/26/2021
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 02/04/2021
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 11/12/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 11/12/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/18/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 08/20/2021
Type: Final
Result: Partial Inspection
Status: Issued
Date: 08/20/2021
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/20/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 08/20/2021
Type: Structural Steel Frame
Result: Approved
Status: Issued
Date: 08/20/2021
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 08/20/2021
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 08/20/2021
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 08/20/2021
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 05/21/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/15/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/09/2021
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 04/09/2021
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 04/09/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 06/29/2021
Type: Elevator Verification
Result: CofO on Hold
Status: Issued
Date: 06/29/2021
Type: Fire Sprinkler Verification
Result: Cancelled
Status: Issued
Date: 06/29/2021
Type: Heat,Vent,A/C Verification
Result: CofO on Hold
Status: Issued
Date: 06/29/2021
Type: Plumbing Verification
Result: CofO on Hold
Status: Issued
Date: 06/30/2021
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
ARK CONSTRUCTION & DEVELOPMENT INC

License number: 438036
Type: B
Phone: Speak with a Permit Expert
Location: PACIFIC PALISADES, CA

Permit Applicant

Principal: FARIBORZ KAMDAR
Type:
Address: 3467 OCEAN VIEW BL, #B, GLENDALE, CA
Phone:
Experience: years
Applicant: HAMLET ZOHRABIANS