Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

(N) SFD WITH ATT/GAR.

Inspection Activity
Date: 05/19/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/22/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 06/08/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/07/2017
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 06/06/2017
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 06/13/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/25/2017
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 10/26/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/03/2017
Type: Underground Mechanical
Result: Insp Scheduled
Status: Issued
Date: 11/07/2017
Type: Sewer
Result: Approved
Status: Issued
Date: 11/09/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/13/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 11/15/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/12/2017
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/19/2017
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/20/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/20/2017
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 12/18/2017
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/12/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 01/12/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 01/12/2018
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 01/16/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/17/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Conditional Approval
Status: Issued
Date: 02/02/2018
Type: HVAC-Rough
Result: Insp Scheduled
Status: Issued
Date: 02/01/2018
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 02/07/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 02/07/2018
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 02/12/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 02/12/2018
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 02/12/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/12/2018
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 02/12/2018
Type: BUILDING-Rough-Frame
Result: Conditional Approval
Status: Issued
Date: 02/16/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 02/23/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 02/20/2018
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 02/27/2018
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 02/27/2018
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 02/26/2018
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 02/26/2018
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 02/27/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 07/27/2018
Type: HVAC-Final
Result: Insp Scheduled
Status: Issued
Date: 07/31/2018
Type: ELECTRICAL-Final
Result: Cancelled
Status: Issued
Date: 08/02/2018
Type: Gas Test
Result: Approved
Status: Issued
Date: 08/08/2018
Type: ELECTRICAL-Final
Result: Cancelled
Status: Issued
Date: 08/13/2018
Type: ELECTRICAL-Final
Result: Conditional Approval
Status: Issued
Date: 08/17/2018
Type: Service/Power Release
Result: Insp Scheduled
Status: Issued
Date: 05/07/2021
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 05/07/2021
Type: Final
Result: Corrections Issued
Status: Issued
Date: 05/07/2021
Type: HVAC-Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/07/2021
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/05/2021
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/05/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 10/05/2021
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 10/05/2021
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/05/2021
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/05/2021
Type: Final
Result: Corrections Issued
Status: Issued
Date: 11/18/2021
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 11/18/2021
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 11/18/2021
Type: Green Building Final
Result: Approved
Status: Issued
Date: 11/18/2021
Type: Special/Order Compliance
Result: Not Ready for Inspection
Status: Issued
Date: 11/18/2021
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/18/2021
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: HVAC-Final
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/25/2022
Type: Special/Order Compliance
Result: Not Ready for Inspection
Status: Issued
Date: 08/09/2022
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/09/2022
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/09/2022
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/15/2022
Type: Pre-Inspection
Result: Approved
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
VILLA NOVA DEVELOPING INC

License number: 706070
Type: B
Phone: Speak with a Permit Expert
Location: SUNLAND, CA

Permit Applicant

Principal: ANDREW NOWACZEK

Type:

Address: 8209A FOOTHILL BLVD, #700, SUNLAND,CA

Phone:

Experience: years

Applicant: MARTA LITWIN