Work Description

NEW 38'-0" X 80'-7", 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CA

Inspection Activity
Date: 05/30/2019
Type: PLUMBING-Final
Result: Approved
Status: Issued
Date: 06/13/2019
Type: Gas Test
Result: Approved
Status: Issued
Date: 06/07/2018
Type: Grading Pre-Inspection
Result: Insp Cancelled
Status: Issued
Date: 06/13/2019
Type: Gas Test
Result: Approved
Status: Issued
Date: 06/25/2018
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 06/25/2018
Type: Sewer
Result: Approved
Status: Issued
Date: 06/26/2018
Type: PLUMBING-Rough
Result: Insp Cancelled
Status: Issued
Date: 07/05/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 07/05/2018
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 07/05/2018
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 07/05/2018
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 07/10/2018
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/10/2018
Type: Deputy Other (see comments)
Result: Conditional Approval
Status: Issued
Date: 07/12/2019
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 07/12/2019
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 07/12/2019
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 07/12/2019
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 07/12/2019
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 07/12/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 08/10/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 07/24/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 07/24/2019
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 07/24/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 07/24/2019
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 08/31/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 08/31/2018
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 08/31/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 08/02/2019
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 08/02/2019
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 07/29/2019
Type: Special/Order Compliance
Result: Insp Cancelled
Status: Issued
Date: 08/08/2019
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 08/08/2019
Type: Final
Result: Partial Approval
Status: Issued
Date: 08/08/2019
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 08/05/2019
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 10/09/2018
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 10/09/2018
Type: HVAC-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/09/2018
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 10/10/2018
Type: HVAC-Rough
Result: Corrections Issued
Status: Issued
Date: 10/10/2018
Type: Gas Test
Result: Approved
Status: Issued
Date: 10/18/2018
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 08/20/2019
Type: Final
Result: No Access for Inspection
Status: Issued
Date: 10/24/2018
Type: Verify Sprinkler Sign Off
Result: Conditional Approval
Status: Issued
Date: 10/24/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 10/24/2018
Type: Shower Pan
Result: Approved
Status: Issued
Date: 10/24/2018
Type: BUILDING-Rough-Frame
Result: Conditional Approval
Status: Issued
Date: 08/27/2019
Type: Final
Result: Conditional Approval
Status: CofO in Progress
Date: 08/28/2019
Type: Inspection
Result: OK for CofO
Status: CofO in Progress
Date: 11/14/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 08/28/2019
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 12/27/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 09/05/2019
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 09/05/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/05/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 03/05/2019
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
T J C HOME BUILDERS LLC

License number: 1025507
Type: B
Phone: Speak with a Permit Expert
Location: ALISO VIEJO, CA

Permit Applicant

Principal: KENNETH JAMES BARCLA CORBEN
Type:
Address: 12005 COLLINS ST, VALLEY VILLAGE ST
Phone:
Experience: years
Applicant: TONI TARDINO