Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

5 STORY 13 UNIT APT WITH SUBTERRANIAN GARAGE

Inspection Activity
Date: 05/31/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/30/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/12/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 06/12/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/13/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 10/21/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/23/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/17/2019
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 06/17/2019
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 12/24/2020
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 06/12/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 06/12/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/13/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 10/30/2019
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 10/31/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 10/30/2019
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/31/2020
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 04/01/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 11/07/2019
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 07/29/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/30/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/02/2019
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/13/2019
Type: Deputy Reinf. Masonry
Result: Insp Cancelled
Status: Issued
Date: 11/13/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/07/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 08/05/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/05/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/24/2020
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 11/18/2019
Type: Deputy Reinf. Masonry
Result: Partial Approval
Status: Issued
Date: 11/22/2019
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/22/2019
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 11/20/2019
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 08/29/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/27/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 09/09/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/14/2019
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 02/14/2019
Type: Grading Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 04/24/2020
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 04/24/2020
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 04/24/2020
Type: Verify Sprinkler Sign Off
Result: Partial Inspection
Status: Issued
Date: 04/16/2019
Type: Deputy Grading
Result: Approved
Status: Issued
Date: 10/16/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/30/2019
Type: Deputy Grading
Result: Approved
Status: Issued
Date: 04/29/2020
Type: Verify Sprinkler Sign Off
Result: Partial Inspection
Status: Issued
Date: 04/30/2020
Type: Insulation
Result: Insp Cancelled
Status: Issued
Date: 04/29/2020
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 04/30/2020
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 04/29/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 12/30/2019
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 05/21/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 05/08/2020
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 01/06/2020
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 01/08/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/23/2020
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 01/24/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 02/03/2020
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 02/05/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/04/2020
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 06/01/2020
Type: Insulation
Result: Cancelled
Status: Issued
Date: 06/05/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 07/27/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 06/23/2021
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 06/23/2021
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 06/23/2021
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 12/06/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 09/23/2021
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 12/23/2021
Type: Interior/Exterior Lathing
Result: Partial Inspection
Status: Issued
Date: 12/23/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/28/2022
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 06/28/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 07/07/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/24/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/05/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 12/14/2023
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 03/15/2024
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 05/13/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
ESAB CONSTRUCTION CORPORATION

License number: 998929
Type: B
Phone: Speak with a Permit Expert
Location: BEVERLY HILLS, CA

Permit Applicant

Principal: EMANUEL SABET

Type:

Address: 15206 VENTURA BL, 201, V N

Phone:

Experience: years

Applicant: -