Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

New 2-story s.f.d. w/ attached garage & uncovered roof deck.(Fully sp

Inspection Activity
Date: 04/18/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 12/08/2017
Type: Underground Mechanical
Result: Insp Scheduled
Status: Issued
Date: 12/15/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 12/18/2017
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 12/18/2017
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 12/18/2017
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 05/25/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 01/17/2018
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 01/17/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 01/17/2018
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 01/17/2018
Type: METHANE-Rough
Result: No Access for Inspection
Status: Issued
Date: 02/05/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 02/05/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/28/2018
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 04/06/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 07/11/2018
Type: PLUMBING-Rough
Result: Insp Cancelled
Status: Issued
Date: 07/27/2018
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 07/25/2018
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 07/27/2018
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: ELECTRICAL-Rough
Result: Insp Scheduled
Status: Issued
Date: 07/25/2018
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 07/27/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 07/25/2018
Type: Gas Test
Result: Approved
Status: Issued
Date: 07/27/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/25/2018
Type: ELECTRICAL-Rough
Result: Corrections Issued
Status: Issued
Date: 07/27/2018
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 08/14/2018
Type: Shower Pan
Result: Approved
Status: Issued
Date: 08/14/2018
Type: Insulation
Result: Conditional Approval
Status: Issued
Date: 08/22/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 08/22/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 09/10/2018
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/25/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 02/13/2019
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: Service/Power Release
Result: Approved
Status: Issued
Date: 02/14/2019
Type: Masonry Wall/Backfill
Result: Cancelled
Status: Issued
Date: 02/13/2019
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: HVAC-Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: BUILDING-Rough-Frame
Result: Conditional Approval
Status: Issued
Date: 02/13/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 02/13/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2019
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 02/27/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: Gas Test
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: METHANE-Rough
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 02/27/2019
Type: BUILDING-Rough-Frame
Result: Insp Cancelled
Status: Issued
Date: 03/04/2019
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 03/06/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/06/2019
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 03/06/2019
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/04/2019
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 03/04/2019
Type: Gas Test
Result: Approved
Status: Issued
Date: 03/06/2019
Type: Green Building Final
Result: Approved
Status: Issued
Date: 03/07/2019
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 03/06/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 03/06/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 03/06/2019
Type: METHANE-Rough
Result: Cancelled
Status: Issued
Date: 03/19/2019
Type: ELECTRICAL-Final
Result: Insp Cancelled
Status: Issued
Date: 03/19/2019
Type: PLUMBING-Final
Result: Insp Cancelled
Status: Issued
Date: 03/19/2019
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 03/20/2019
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 03/26/2019
Type: ELECTRICAL-Final
Result: Approved
Status: CofO in Progress
Date: 03/26/2019
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 03/29/2019
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/26/2019
Type: PLUMBING-Final
Result: Approved
Status: CofO in Progress
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
SOUMEKH MICHAEL N

License number: 773770
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: MICHAEL NAVID SOUMEKH

Type:

Address:

Phone:

Experience: years

Applicant: NOREENA SCHERER