Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

new 48 units (5 of which are live/work units tier-1 on the ground floo

Inspection Activity
Date: 04/16/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/16/2018
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 06/12/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 06/12/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/23/2018
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 03/25/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 06/20/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 06/21/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 02/08/2018
Type: Grading Pre-Inspection
Result: Corrections Issued
Status: Issued
Date: 02/15/2018
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 02/15/2018
Type: Grading Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 02/12/2018
Type: Grading Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 06/12/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 06/12/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 03/22/2018
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 11/01/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/01/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 10/31/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/01/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 07/01/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/02/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/04/2018
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 07/02/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/01/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/01/2019
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/02/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 07/11/2019
Type: Deputy Reinf. Concrete
Result: Insp Cancelled
Status: Issued
Date: 08/14/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/16/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/04/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 07/26/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/22/2018
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 07/24/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/31/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/02/2019
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 11/14/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 10/11/2018
Type: METHANE-Subgrade
Result: Partial Approval
Status: Issued
Date: 10/12/2018
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/11/2018
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/16/2018
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/17/2018
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/19/2018
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 10/17/2018
Type: METHANE-Rough
Result: Partial Inspection
Status: Issued
Date: 10/18/2018
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 08/22/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/21/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/25/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/25/2018
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/24/2018
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/26/2018
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 10/23/2018
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/22/2018
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/25/2018
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 11/07/2018
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 11/09/2018
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 11/07/2018
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 11/07/2018
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 11/16/2018
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 11/16/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 11/15/2018
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 11/16/2018
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 12/28/2018
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 12/27/2018
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 01/04/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 01/03/2019
Type: Reinforced Masonry Frame
Result: Partial Inspection
Status: Issued
Date: 01/08/2019
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 01/11/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 01/08/2019
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 01/07/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 01/08/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 01/17/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 01/15/2019
Type: Reinforced Masonry Frame
Result: Partial Inspection
Status: Issued
Date: 01/23/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 01/31/2019
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 02/01/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 02/08/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 09/17/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 02/15/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 02/21/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 02/22/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 02/22/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 03/01/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 03/05/2019
Type: Reinforced Masonry Frame
Result: Partial Inspection
Status: Issued
Date: 03/13/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 10/01/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/02/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 03/18/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 03/21/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 10/02/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 03/29/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 03/26/2019
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 12/10/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 10/10/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/05/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 10/10/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/09/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/08/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 04/09/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 04/12/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 04/19/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 04/19/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 04/19/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/17/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 10/18/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/17/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 10/18/2019
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 04/22/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 04/26/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/03/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 04/30/2019
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 05/01/2020
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/20/2019
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 05/24/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 05/22/2019
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 05/21/2019
Type: Reinforced Concrete Frame
Result: Corrections Issued
Status: Issued
Date: 09/03/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/04/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 01/07/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 01/13/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 01/31/2020
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 01/28/2020
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/19/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 02/04/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 02/06/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 02/14/2020
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 02/19/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 03/02/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 08/12/2021
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 08/12/2021
Type: Electrical Verification
Result: OK for CofO
Status: Issued
Date: 08/10/2021
Type: Green Building Final
Result: Approved
Status: Issued
Date: 08/13/2021
Type: Elevator Verification
Result: CofO on Hold
Status: Issued
Date: 01/12/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 01/15/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 07/14/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 08/12/2021
Type: Plumbing Verification
Result: CofO on Hold
Status: Issued
Date: 08/04/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 10/16/2020
Type: Wall Anchors
Result: Not Ready for Inspection
Status: Issued
Date: 10/14/2020
Type: Wall Anchors
Result: Approved
Status: Issued
Date: 11/12/2020
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 12/11/2020
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 12/10/2020
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 12/16/2020
Type: Wall Anchors
Result: Approved
Status: Issued
Date: 04/09/2021
Type: Pre-Inspection
Result: Cancelled
Status: Issued
Date: 09/03/2021
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/09/2021
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/08/2021
Type: Elevator Verification
Result: OK for CofO
Status: Issued
Date: 09/07/2021
Type: Plumbing Verification
Result: Pending
Status: Issued
Date: 09/21/2021
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/16/2022
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 08/04/2022
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/12/2022
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 08/10/2022
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 08/24/2022
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 08/24/2022
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 08/24/2022
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
SMA BUILDERS INC

License number: 457725
Type: B
Phone: Speak with a Permit Expert
Location: VAN NUYS, CA

Permit Applicant

Principal: SHAWN MARC ANTIN

Type:

Address:

Phone:

Experience: years

Applicant: SAM GHANOUNI