Bldg-Addition Permit

PCIS Permit#: 16014-30000-06070

Address: 1415 ORIOLE, Los Angeles, 90069

Status: CofO Issued

Status Date: 09/08/2019

Tract: P M 3679

Property Identifier: Block: , Lot: A, Zone: RE15-1-H

Assessor Information: Book: 5560, Page: 6, Parcel: 16

Census Tract: 1943

Work Description

Remodel and addition to (e) 2-story s.f.d. with attached garage, new b

Inspection Activity
Date: 04/25/2017
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 04/25/2017
Type: Grounding or Bonding
Result: Approved
Status: Issued
Date: 05/24/2017
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 05/24/2017
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/02/2017
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 06/05/2017
Type: Deputy Reinf. Concrete
Result: No Access for Inspection
Status: Issued
Date: 06/15/2017
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 10/10/2017
Type: Reinforced Concrete Frame
Result: Conditional Approval
Status: Issued
Date: 10/20/2017
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 10/23/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 11/08/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 11/15/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 11/15/2017
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 12/05/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 01/05/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 01/19/2018
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 01/19/2018
Type: HVAC-Rough
Result: Insp Scheduled
Status: Issued
Date: 01/19/2018
Type: ELECTRICAL-Rough
Result: Insp Scheduled
Status: Issued
Date: 01/19/2018
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 01/24/2018
Type: Sewer
Result: Conditional Approval
Status: Issued
Date: 01/22/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 01/22/2018
Type: BUILDING-Rough-Frame
Result: Conditional Approval
Status: Issued
Date: 01/29/2018
Type: Sewer
Result: Conditional Approval
Status: Issued
Date: 01/31/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 02/06/2018
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/15/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 02/21/2018
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 02/21/2018
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 02/21/2018
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 03/12/2018
Type: Insulation
Result: Approved
Status: Issued
Date: 07/06/2018
Type: ELECTRICAL-Rough
Result: Insp Scheduled
Status: Issued
Date: 04/07/2018
Type: Public Counter
Result: Completed
Status: Issued
Date: 04/06/2018
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 10/03/2018
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2018
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/03/2018
Type: HVAC-Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/16/2018
Type: ELECTRICAL-Final
Result: Insp Cancelled
Status: Issued
Date: 10/16/2018
Type: PLUMBING-Final
Result: Insp Cancelled
Status: Issued
Date: 10/16/2018
Type: HVAC-Final
Result: Insp Cancelled
Status: Issued
Date: 11/08/2018
Type: ELECTRICAL-Final
Result: Partial Inspection
Status: Issued
Date: 11/08/2018
Type: HVAC-Final
Result: Partial Inspection
Status: Issued
Date: 11/08/2018
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 08/30/2019
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 09/03/2019
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 01/15/2019
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 09/08/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/08/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/08/2019
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 01/30/2019
Type: ELECTRICAL-Final
Result: Partial Inspection
Status: Issued
Date: 01/30/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 01/30/2019
Type: PLUMBING-Final
Result: Partial Inspection
Status: Issued
Date: 01/30/2019
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 01/30/2019
Type: HVAC-Final
Result: Partial Inspection
Status: Issued
Date: 01/30/2019
Type: Green Building Final
Result: Approved
Status: Issued
Date: 01/31/2019
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 01/30/2019
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/30/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 01/30/2019
Type: Final
Result: Corrections Issued
Status: Issued
Date: 03/08/2019
Type: Grading Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 04/08/2019
Type: Final
Result: Partial Inspection
Status: Issued
Date: 04/16/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/21/2019
Type: Final
Result: Insp Cancelled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
MATT CONSTRUCTION CORPORATION

License number: 631020
Type: A
Phone: Speak with a Permit Expert
Location: SANTA FE SPRINGS, CA

Permit Applicant

Principal: STEVEN FRANCIS MATT
Type:
Address:
Phone:
Experience: years
Applicant: CHRIS DRUGAN