Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

Tenant Improvement, exterior remodel, enclosing loading dock ( 325sqft

Inspection Activity
Date: 04/04/2017
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 04/04/2017
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 04/04/2017
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/10/2017
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/10/2017
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/10/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 05/23/2017
Type: METHANE-Rough
Result: Partial Inspection
Status: Issued
Date: 05/23/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 05/23/2017
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 05/23/2017
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/31/2017
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/31/2017
Type: METHANE-Rough
Result: Partial Inspection
Status: Issued
Date: 05/31/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2017
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 10/06/2017
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 10/06/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 10/06/2017
Type: METHANE-Final
Result: Insp Scheduled
Status: Issued
Date: 10/10/2017
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 10/11/2017
Type: AIM Verification
Result: Not Applicable
Status: Issued
Date: 10/10/2017
Type: Public Counter
Result: Completed
Status: Issued
Date: 10/10/2017
Type: Heat,Vent,A/C Verification
Result: CofO on Hold
Status: Issued
Date: 10/10/2017
Type: Grading Verification
Result: Not Applicable
Status: Issued
Date: 10/10/2017
Type: Plumbing Verification
Result: CofO on Hold
Status: Issued
Date: 10/10/2017
Type: Green Code Verification
Result: CofO on Hold
Status: Issued
Date: 10/24/2017
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 10/24/2017
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2017
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/24/2017
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/26/2017
Type: Special/Order Compliance
Result: Partial Approval
Status: Issued
Date: 10/24/2017
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 11/09/2017
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 11/08/2017
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/09/2017
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 11/09/2017
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 11/17/2017
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 11/17/2017
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: CofO in Progress
Date: 11/13/2017
Type: Green Building Final
Result: Approved
Status: CofO in Progress
Date: 11/13/2017
Type: Electrical Verification
Result: OK for CofO
Status: CofO in Progress
Date: 11/13/2017
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 11/13/2017
Type: Plumbing Verification
Result: OK for CofO
Status: CofO in Progress
Date: 11/20/2017
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 11/20/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 11/20/2017
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
CALCO CONSTRUCTION SERVICES INC

License number: 955140
Type: B
Phone: Speak with a Permit Expert
Location: ANAHEIM, CA

Permit Applicant

Principal: MICHAEL LE ROY HOTVEDT

Type:

Address: 3600 BIRCH ST., NEWPORT BEACH, CA

Phone:

Experience: years

Applicant: ELENA MASHIN