Fire Sprinkler Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW FIRE PROTECTION SYSTEM FOR PARKING LEVELS AND STANDPIPES IN EXISTI

Inspection Activity
Date: 04/18/2017
Type: Standpipe Hydro
Result: Partial Approval
Status: Issued
Date: 04/19/2017
Type: Standpipe Hydro
Result: Partial Approval
Status: Issued
Date: 04/20/2017
Type: Standpipe Hydro
Result: Corrections Issued
Status: Issued
Date: 10/02/2017
Type: Weld
Result: Partial Approval
Status: Issued
Date: 10/05/2017
Type: Weld
Result: Insp Scheduled
Status: Issued
Date: 10/02/2017
Type: Standpipe Hydro
Result: Partial Approval
Status: Issued
Date: 10/11/2017
Type: Weld
Result: Insp Cancelled
Status: Issued
Date: 10/16/2017
Type: Weld
Result: Partial Approval
Status: Issued
Date: 11/03/2017
Type: Weld
Result: Insp Scheduled
Status: Issued
Date: 06/12/2019
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 06/12/2019
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 10/31/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 07/11/2018
Type: Overhead Hydro
Result: Partial Inspection
Status: Issued
Date: 07/11/2018
Type: Rough
Result: OK to Expire Permit
Status: Issued
Date: 07/10/2019
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 08/15/2019
Type: Rough
Result: Insp Cancelled
Status: Issued
Date: 08/15/2019
Type: Overhead Hydro
Result: Insp Cancelled
Status: Issued
Date: 07/15/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 07/30/2019
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 07/30/2019
Type: Rough
Result: Conditional Approval
Status: Issued
Date: 11/14/2019
Type: Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/14/2019
Type: Overhead Hydro
Result: Partial Inspection
Status: Issued
Date: 08/19/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 08/19/2019
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 11/20/2019
Type: Underground Hydro
Result: Insp Scheduled
Status: Issued
Date: 11/20/2019
Type: Underground Flush
Result: Insp Scheduled
Status: Issued
Date: 11/20/2019
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 11/20/2019
Type: Fire Pump Hydro
Result: Insp Scheduled
Status: Issued
Date: 11/20/2019
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 11/19/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 11/25/2019
Type: Underground Flush
Result: Partial Approval
Status: Issued
Date: 11/25/2019
Type: Underground Hydro
Result: Partial Approval
Status: Issued
Date: 11/25/2019
Type: Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/25/2019
Type: Overhead Hydro
Result: Not Ready for Inspection
Status: Issued
Date: 09/10/2019
Type: Overhead Hydro
Result: Insp Cancelled
Status: Issued
Date: 09/10/2019
Type: Rough
Result: Insp Cancelled
Status: Issued
Date: 09/12/2019
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 09/19/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 12/03/2019
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 12/03/2019
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 09/25/2019
Type: Overhead Hydro
Result: Not Ready for Inspection
Status: Issued
Date: 09/25/2019
Type: Rough
Result: Corrections Issued
Status: Issued
Date: 10/01/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 10/04/2019
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 10/04/2019
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 12/13/2019
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 03/28/2019
Type: Weld
Result: Approved
Status: Issued
Date: 12/13/2019
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 12/18/2019
Type: Rough
Result: Partial Approval
Status: Issued
Date: 12/18/2019
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 04/30/2020
Type: Overhead Hydro
Result: Partial Inspection
Status: Issued
Date: 04/30/2020
Type: Rough
Result: Conditional Approval
Status: Issued
Date: 09/01/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 09/01/2020
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 09/01/2020
Type: Final
Result: Cancelled
Status: Issued
Date: 01/10/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 01/06/2020
Type: Standpipe Hydro
Result: Partial Approval
Status: Issued
Date: 01/06/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 01/16/2020
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 01/14/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 01/16/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 05/12/2020
Type: Fire Pump Test
Result: Partial Inspection
Status: Issued
Date: 05/12/2020
Type: Public Counter
Result: Completed
Status: Issued
Date: 05/12/2020
Type: Fire Pump Test
Result: Off-Hour Fees Due
Status: Issued
Date: 05/12/2020
Type: Fire Pump Test
Result: Approved
Status: Issued
Date: 01/29/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 01/30/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 01/30/2020
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 01/29/2020
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 01/31/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 01/31/2020
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 09/11/2020
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 02/07/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 02/07/2020
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 02/14/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 02/14/2020
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 02/19/2020
Type: Fire Pump Test
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Standpipe Hydro
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 02/27/2020
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 02/26/2020
Type: Overhead Hydro
Result: Partial Approval
Status: Issued
Date: 02/28/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 02/27/2020
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 02/26/2020
Type: Rough
Result: Partial Approval
Status: Issued
Date: 02/28/2020
Type: Overhead Hydro
Result: Insp Scheduled
Status: Issued
Date: 03/03/2020
Type: Fire Dept Connection Flush
Result: Approved
Status: Issued
Date: 03/12/2020
Type: Final
Result: Corrections Issued
Status: Issued
Date: 03/10/2020
Type: Final
Result: Corrections Issued
Status: Issued
Date: 03/11/2020
Type: Final
Result: Corrections Issued
Status: Issued
Date: 09/23/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 06/16/2020
Type: Special/Order Compliance
Result: Insp Cancelled
Status: Issued
Date: 07/09/2020
Type: Special/Order Compliance
Result: Not Ready for Inspection
Status: Issued
Date: 07/09/2020
Type: Special/Order Compliance
Result: Off-Hour Fees Due
Status: Issued
Date: 09/23/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 07/30/2020
Type: Public Counter
Result: Completed
Status: Issued
Date: 07/30/2020
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 09/30/2020
Type: Final
Result: Cancelled
Status: Issued
Date: 10/06/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 11/29/2021
Type: Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/25/2021
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 05/26/2021
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 05/28/2021
Type: Rough
Result: Insp Scheduled
Status: Issued
Date: 11/29/2021
Type: Public Counter
Result: Completed
Status: Issued
Date: 11/29/2021
Type: Rough
Result: Partial Inspection
Status: Issued
Date: 06/02/2021
Type: Rough
Result: Partial Approval
Status: Issued
Date: 06/11/2021
Type: Rough
Result: Partial Approval
Status: Issued
Date: 08/06/2021
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 09/15/2022
Type: Inspection
Result: Permit Finaled
Status: Permit Finaled
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
STREAMLINE FIRE PROTECTION INC

License number: 931653
Type: C16
Phone: Speak with a Permit Expert
Location: LAKEWOOD, CA

Permit Applicant

Principal: LUKE DUANE DANIEL

Type:

Address: 3700 INDUSTRY AVE, #104, LAKEWOOD, CA

Phone:

Experience: years

Applicant: ERWIN ROSALES