Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

ADDTION TWO STORY OFFICE AND RETAIL FURNITURE (Major Appliances store,

Inspection Activity
Date: 10/03/2017
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 10/02/2017
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 10/03/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/06/2017
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 10/13/2017
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 10/10/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/24/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 10/23/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/23/2017
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/03/2017
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/06/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/07/2017
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/08/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/15/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/14/2017
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/14/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/16/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/17/2017
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/13/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/22/2017
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 11/22/2017
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/20/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/27/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/29/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/28/2017
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 11/29/2017
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 12/06/2017
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/23/2018
Type: Heat,Vent,A/C Verification
Result: Pending
Status: Issued
Date: 05/23/2018
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 12/27/2017
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/27/2017
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/23/2018
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 05/23/2018
Type: Pressure Vessel Verification
Result: OK for CofO
Status: Issued
Date: 05/22/2018
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/23/2018
Type: Plumbing Verification
Result: CofO on Hold
Status: Issued
Date: 01/11/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/12/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/12/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 01/18/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/24/2018
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 02/02/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/31/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/05/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/09/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 02/08/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/06/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/05/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/07/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/16/2018
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 02/16/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 02/12/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/20/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/18/2018
Type: SUSMP-Std. Urban Storm Water
Result: Not Ready for Inspection
Status: Issued
Date: 06/18/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 06/18/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Wood Frame
Result: Approved
Status: Issued
Date: 03/01/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/26/2018
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/26/2018
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 06/18/2018
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 06/18/2018
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 06/18/2018
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 06/18/2018
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/07/2018
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 03/07/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/21/2018
Type: SUSMP-Std. Urban Storm Water
Result: Partial Inspection
Status: Issued
Date: 07/09/2018
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 08/27/2018
Type: SUSMP-Std. Urban Storm Water
Result: Not Ready for Inspection
Status: Issued
Date: 08/27/2018
Type: Electrical Verification
Result: OK for CofO
Status: Issued
Date: 08/27/2018
Type: Green Building Final
Result: Approved
Status: Issued
Date: 08/27/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 08/27/2018
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 08/27/2018
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 08/27/2018
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 08/27/2018
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/27/2018
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 12/27/2018
Type: Special/Order Compliance
Result: Corrections Issued
Status: Issued
Date: 01/07/2019
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 01/07/2019
Type: SUSMP-Std. Urban Storm Water
Result: Approved
Status: CofO in Progress
Date: 01/08/2019
Type: SUSMP-Std. Urban Storm Water
Result: Approved
Status: CofO in Progress
Date: 01/08/2019
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/11/2019
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 03/11/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 03/11/2019
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
H & K'S VIEW CONSTRUCTIONS INC

License number: 603224
Type: B
Phone: Speak with a Permit Expert
Location: SHERMAN OAKS, CA

Permit Applicant

Principal: PAUL YU KANG

Type:

Address: 550 S WILTON PL, LOS ANGELES, CA

Phone:

Experience: years

Applicant: CHAN KWAK