Bldg-New Permit

PCIS Permit#: 17010-10000-02378

Address: 11401 PORTER RANCH, Los Angeles, 91326

Status: CofO Issued

Status Date: 05/26/2021

Tract: TR 53783-C

Property Identifier: Block: , Lot: 1, Zone: (T)C4-2D

Assessor Information: Book: 2246, Page: 20, Parcel: 15

Census Tract: 1082.02

Work Description

PROPOSED 20 UNIT APARTMENT BLDG. BLDG #2, TYPE VA CONSTRUCTION, 3-STOR

Inspection Activity
Date: 06/21/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 06/20/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/20/2019
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 10/28/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 08/15/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 11/06/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 07/26/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 07/22/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 07/24/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/30/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 08/07/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 08/26/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 08/27/2019
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 11/22/2019
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 09/03/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/25/2019
Type: Special/Order Compliance
Result: Not Ready for Inspection
Status: Issued
Date: 11/25/2019
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 12/02/2019
Type: Special/Order Compliance
Result: Corrections Issued
Status: Issued
Date: 09/23/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 09/26/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 12/11/2019
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 09/30/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 10/03/2019
Type: Light Gage Steel Frame
Result: Partial Inspection
Status: Issued
Date: 12/13/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 12/12/2019
Type: Insulation
Result: Cancelled
Status: Issued
Date: 10/09/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/12/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 04/12/2019
Type: SWPPP-Const. Storm Water
Result: Insp Scheduled
Status: Issued
Date: 04/22/2021
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 04/22/2021
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 04/22/2021
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 10/17/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/15/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 10/15/2019
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 04/22/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/24/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/22/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/18/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 05/02/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/01/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 05/01/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/27/2020
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 12/26/2019
Type: Interior/Exterior Lathing
Result: Cancelled
Status: Issued
Date: 12/26/2019
Type: Insulation
Result: Cancelled
Status: Issued
Date: 12/26/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Cancelled
Status: Issued
Date: 04/29/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 01/02/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 12/31/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 01/10/2020
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/10/2020
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 01/06/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 01/09/2020
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 05/05/2020
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 01/16/2020
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 01/15/2020
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 01/14/2020
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 01/21/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/21/2020
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 01/21/2020
Type: SWPPP-Const. Storm Water
Result: Completed
Status: Issued
Date: 01/21/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 01/21/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/13/2020
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 04/22/2021
Type: Grading Verification
Result: Not Applicable
Status: Issued
Date: 01/30/2020
Type: Light Gage Steel Frame
Result: Partial Inspection
Status: Issued
Date: 02/05/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/03/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/05/2020
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 02/12/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/13/2020
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 02/21/2020
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 03/06/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 03/12/2020
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 07/08/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Insulation
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 07/08/2020
Type: Wood Frame
Result: Approved
Status: Issued
Date: 05/04/2021
Type: Special/Order Compliance
Result: Partial Inspection
Status: CofO in Progress
Date: 11/05/2020
Type: SWPPP-Const. Storm Water
Result: Not Required
Status: Issued
Date: 11/05/2020
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/05/2020
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 11/05/2020
Type: SUSMP-Std. Urban Storm Water
Result: Not Ready for Inspection
Status: Issued
Date: 11/05/2020
Type: Smoke Detectors
Result: Partial Inspection
Status: Issued
Date: 11/05/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 05/04/2021
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 05/05/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 11/09/2020
Type: TCO Grading Verification
Result: Completed (special insp)
Status: Issued
Date: 11/09/2020
Type: TCO Heat,Vent,A/C Verification
Result: Completed (special insp)
Status: Issued
Date: 11/10/2020
Type: TCO Sprinkler Verification
Result: Completed (special insp)
Status: Issued
Date: 11/09/2020
Type: TCO Plumbing Verification
Result: Completed (special insp)
Status: Issued
Date: 11/09/2020
Type: TCO Electrical Verification
Result: Completed (special insp)
Status: Issued
Date: 05/26/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 05/26/2021
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 05/26/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/01/2021
Type: Final
Result: Partial Inspection
Status: Issued
Date: 04/01/2021
Type: SUSMP-Std. Urban Storm Water
Result: Approved
Status: Issued
Date: 04/01/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 04/01/2021
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 04/01/2021
Type: Green Building Final
Result: Approved
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
R C I BUILDERS INC

License number: 835114
Type: B
Phone: Speak with a Permit Expert
Location: THOUSAND OAKS, CA

Permit Applicant

Principal: STEVEN ANDREW RICE
Type:
Address: 555 W. 5TH ST., 35TH FLOOR, LOS ANGELES, CA
Phone:
Experience: years
Applicant: TOM MCDONOUGH