Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

MIXED USE: OFFICE & 4 STORY 36 UNITS APT WITH FIRST FLOOR GARAGE. 11%

Inspection Activity
Date: 05/28/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 05/31/2019
Type: Public Counter
Result: Completed
Status: Issued
Date: 05/31/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/31/2019
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 05/29/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/14/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/12/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/10/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/10/2019
Type: Masonry Wall/Backfill
Result: Insp Cancelled
Status: Issued
Date: 06/10/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/11/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 10/21/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 03/27/2020
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 06/20/2019
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 06/17/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/17/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/20/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/20/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/18/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/19/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/21/2019
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 06/21/2019
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 06/21/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 06/21/2019
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 06/20/2019
Type: Masonry Wall/Backfill
Result: Insp Cancelled
Status: Issued
Date: 06/21/2019
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 06/14/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/12/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/10/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/10/2019
Type: Masonry Wall/Backfill
Result: Insp Cancelled
Status: Issued
Date: 06/10/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/11/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 07/02/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 07/02/2019
Type: Public Counter
Result: Completed
Status: Issued
Date: 07/01/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 07/03/2019
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 04/03/2020
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 04/03/2020
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 07/11/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/08/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/10/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/10/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/14/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/15/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 11/08/2019
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 11/05/2019
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/07/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/05/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 04/03/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 11/12/2019
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 11/15/2019
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 11/14/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 11/13/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 08/16/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 04/10/2020
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 04/08/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 08/23/2019
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 08/23/2019
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 08/23/2019
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 08/20/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/23/2019
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 11/21/2019
Type: Pre-Inspection
Result: Conditional Approval
Status: Issued
Date: 11/20/2019
Type: Pre-Inspection
Result: Cancelled
Status: Issued
Date: 11/19/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/30/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/28/2019
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 08/29/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 04/21/2021
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 09/06/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 09/04/2019
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 09/05/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/04/2019
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 09/04/2019
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 09/03/2019
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 09/06/2019
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 04/13/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/26/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 04/16/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 09/13/2019
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 09/13/2019
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 09/12/2019
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 09/13/2019
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 09/13/2019
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 12/02/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 09/23/2019
Type: Wood Frame
Result: Conditional Approval
Status: Issued
Date: 09/23/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 09/23/2019
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/22/2020
Type: Wall Anchors
Result: Partial Approval
Status: Issued
Date: 04/22/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 04/20/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 12/09/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 12/10/2019
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 10/08/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/09/2019
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 10/07/2019
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 10/10/2019
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 10/15/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/19/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 12/16/2019
Type: Wall Anchors
Result: Not Ready for Inspection
Status: Issued
Date: 12/16/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 12/16/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 04/29/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 12/24/2019
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/23/2019
Type: Pre-Inspection
Result: No Access for Inspection
Status: Issued
Date: 12/24/2019
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 12/24/2019
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/24/2019
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 05/24/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/04/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/06/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 04/21/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 05/11/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/24/2020
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 01/23/2020
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 01/22/2020
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 01/29/2020
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 01/31/2020
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 01/28/2020
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 09/09/2020
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 05/22/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/04/2020
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 02/07/2020
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 02/12/2020
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 02/26/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 02/26/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/26/2020
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 03/02/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/06/2020
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 03/02/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/16/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 06/23/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/07/2020
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 07/14/2020
Type: Light Gage Steel Frame
Result: Partial Inspection
Status: Issued
Date: 07/16/2020
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 04/27/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/27/2021
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 07/24/2020
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 07/23/2020
Type: Special/Order Compliance
Result: Partial Approval
Status: Issued
Date: 07/28/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 04/27/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 12/18/2020
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 12/18/2020
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 12/18/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 12/18/2020
Type: Final
Result: Partial Inspection
Status: Issued
Date: 12/18/2020
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 12/18/2020
Type: Green Building Final
Result: Partial Inspection
Status: Issued
Date: 12/18/2020
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 12/18/2020
Type: Structural Steel Frame
Result: Approved
Status: Issued
Date: 12/18/2020
Type: Wood Frame
Result: Approved
Status: Issued
Date: 03/02/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 03/02/2021
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/02/2021
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 03/02/2021
Type: Final
Result: Partial Inspection
Status: Issued
Date: 03/11/2021
Type: Green Building Final
Result: Approved
Status: Issued
Date: 03/11/2021
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 03/26/2021
Type: Final
Result: Not Ready for Inspection
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
B E C

License number: 517842
Type: B
Phone: Speak with a Permit Expert
Location: GLENDALE, CA

Permit Applicant

Principal: MARDIROS ARTINE BOULDOUKIAN

Type:

Address: 440 W COLORADO ST, #200, GLENDALE, CA

Phone:

Experience: years

Applicant: EDDY ALLAHVERDIAN