Bldg-Alter/Repair Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

INTERIOR IMPROVEMENT OF ( E ) FEDEX SORTING WAREHOUSE : UPAGRADE REST

Inspection Activity
Date: 10/04/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/05/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/06/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 10/03/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/02/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/11/2017
Type: Structural Steel Frame
Result: Cancelled
Status: Issued
Date: 10/11/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/13/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 10/12/2017
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 10/13/2017
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/20/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 10/16/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/17/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 10/20/2017
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 10/18/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/17/2017
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 10/19/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/01/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/02/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/30/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 10/31/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/03/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 11/09/2017
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 11/09/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 11/08/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/16/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/14/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/15/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/21/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/22/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 04/30/2018
Type: Light Gage Steel Frame
Result: Approved
Status: Issued
Date: 05/02/2018
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 05/03/2018
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/30/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/29/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/01/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 11/28/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/05/2017
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 12/05/2017
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Date: 12/06/2017
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 12/05/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/06/2017
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 12/12/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/15/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 12/11/2017
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/15/2017
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 12/11/2017
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 12/12/2017
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 12/20/2017
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 12/29/2017
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/09/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/18/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/19/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/26/2018
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/26/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/25/2018
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/06/2018
Type: Green Building Final
Result: Approved
Status: Issued
Date: 06/06/2018
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV No Gas
Status: Issued
Date: 06/06/2018
Type: Final
Result: Partial Inspection
Status: Issued
Date: 01/29/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 02/02/2018
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 01/31/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 02/01/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 01/30/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 06/06/2018
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 06/28/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 06/28/2018
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/17/2018
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 07/19/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
SWINERTON BUILDERS

License number: 92
Type: B
Phone: Speak with a Permit Expert
Location: SAN FRANCISCO, CA

Permit Applicant

Principal: GARY JOSEPH RAFFERTY

Type:

Address:

Phone:

Experience: years

Applicant: ERIC