Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

LOCKER ROOM BUILDING (~5200 SF) WITH POOL EQUIPMENT/STORAGE 1 STORY WI

Inspection Activity
Date: 03/27/2020
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 03/23/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/27/2020
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 06/19/2019
Type: Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 04/02/2020
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/01/2020
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/14/2019
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 08/13/2019
Type: Masonry Wall/Backfill
Result: Cancelled
Status: Issued
Date: 08/15/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/04/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/04/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/23/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/24/2019
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 04/01/2020
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 07/31/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 08/01/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/01/2019
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 11/14/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 11/13/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 11/14/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/12/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 11/14/2019
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 08/08/2019
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 08/09/2019
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 08/06/2019
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 08/05/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/09/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/12/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 04/10/2020
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2020
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 08/19/2019
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/22/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 08/19/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 11/18/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/29/2019
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 08/29/2019
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/25/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 04/17/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 04/15/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 04/17/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/16/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/17/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/24/2019
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 04/21/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/09/2019
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 10/11/2019
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 10/17/2019
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 10/15/2019
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 10/16/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/19/2019
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 12/20/2019
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 04/29/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/01/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 01/09/2020
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 01/10/2020
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/13/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 01/14/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 01/22/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/29/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 01/31/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 01/31/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/18/2020
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 05/18/2020
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/18/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/29/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/19/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 03/05/2020
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 03/04/2020
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 06/08/2020
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 06/12/2020
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 09/23/2020
Type: T-Bar Ceiling
Result: Approved
Status: Issued
Date: 06/15/2020
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 06/15/2020
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/18/2020
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 06/24/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/24/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 09/23/2020
Type: T-Bar Ceiling
Result: Approved
Status: Issued
Date: 07/16/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 07/23/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 07/31/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 10/07/2020
Type: AIM Verification
Result: Not Applicable
Status: Issued
Date: 10/07/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 10/07/2020
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/07/2020
Type: Electrical Verification
Result: OK for CofO
Status: Issued
Date: 08/10/2020
Type: T-Bar Ceiling
Result: Cancelled
Status: Issued
Date: 10/07/2020
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 10/07/2020
Type: Wood Frame
Result: Approved
Status: Issued
Date: 10/07/2020
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 10/07/2020
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 10/07/2020
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 10/07/2020
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/16/2020
Type: Final
Result: Partial Approval
Status: Issued
Date: 10/16/2020
Type: Green Building Final
Result: Approved
Status: Issued
Date: 10/23/2020
Type: Inspection
Result: OK for CofO
Status: CofO in Progress
Date: 10/23/2020
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 10/29/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 10/29/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 10/29/2020
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
VIOLE' T CONSTRUCTION CO INC

License number: 283354
Type: B
Phone: Speak with a Permit Expert
Location: TARZANA, CA

Permit Applicant

Principal: TIMOTHY LAURENCE VIOLE'

Type:

Address: 5900 WILSHIRE BLVD STE 1540, LOS ANGELES, CA

Phone:

Experience: years

Applicant: ANNE WONG