Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

New 4-story 26-unit TOC affordable housing apartment building VA over

Inspection Activity
Date: 12/22/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/23/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/21/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/22/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/20/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/21/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/23/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/19/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 04/10/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 12/27/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/28/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/29/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/30/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 04/14/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 04/14/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 04/14/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 01/03/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/08/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/16/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 12/16/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 02/06/2023
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 04/20/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 05/23/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 05/21/2024
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 05/23/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/21/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 05/20/2024
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 05/21/2024
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 10/03/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 10/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/13/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 05/28/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/28/2024
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/28/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/28/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/17/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/23/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 10/26/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/25/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/23/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/27/2023
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 10/27/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/23/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 10/27/2023
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 10/27/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 10/27/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 06/07/2024
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 06/04/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 06/06/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 10/31/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Off-Hour Fees Due
Status: Issued
Date: 11/06/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 07/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/13/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 07/27/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/26/2023
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 07/25/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 07/24/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 07/26/2023
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 07/26/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/17/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 11/14/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/03/2023
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 08/01/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/20/2023
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 11/21/2023
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 11/20/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 11/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/09/2023
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/11/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/09/2023
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/09/2023
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 08/09/2023
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 08/07/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 11/20/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 11/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Off-Hour Fees Due
Status: Issued
Date: 06/20/2024
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 06/17/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/20/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 06/17/2024
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 08/19/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/19/2023
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 08/19/2023
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 06/20/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/17/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/20/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/17/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/31/2023
Type: METHANE-Barrier
Result: Insp Scheduled
Status: Issued
Date: 08/30/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/31/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/31/2023
Type: METHANE-Subgrade
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/08/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/08/2023
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 09/08/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/08/2023
Type: METHANE-Subgrade
Result: Partial Approval
Status: Issued
Date: 09/15/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/15/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 06/24/2024
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 12/16/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 12/16/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Off-Hour Fees Due
Status: Issued
Date: 09/20/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/21/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/18/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/21/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/21/2023
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 09/21/2023
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 12/18/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 12/18/2023
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 07/02/2024
Type: Drywall Nailing
Result: Partial Inspection
Status: Issued
Date: 12/28/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/29/2023
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 01/12/2024
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 01/12/2024
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 01/11/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 01/12/2024
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 01/08/2024
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 01/10/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: No Access for Inspection
Status: Issued
Date: 01/12/2024
Type: Wood Frame
Result: Insp Scheduled
Status: Issued
Date: 01/17/2024
Type: Special/Order Compliance
Result: Corrections Issued
Status: Issued
Date: 01/15/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 01/29/2024
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 02/15/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/15/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 03/07/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 03/07/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 03/15/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 03/13/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 03/14/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 03/13/2024
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 03/13/2024
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 03/19/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/18/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 03/19/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/19/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 03/19/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 03/27/2024
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 04/01/2024
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 04/01/2024
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 04/03/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 04/01/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/01/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/04/2024
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 04/04/2024
Type: Drywall Nailing
Result: Corrections Issued
Status: Issued
Date: 04/01/2024
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 04/04/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/02/2024
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 04/01/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/03/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/04/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/04/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/02/2024
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 04/19/2024
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 04/23/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 04/24/2024
Type: Deputy Wood Construction
Result: Approved
Status: Issued
Date: 04/24/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 04/30/2024
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 05/01/2024
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 05/01/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/09/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/08/2024
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 05/06/2024
Type: Wood Frame
Result: Partial Approval
Status: Issued
Date: 05/06/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/06/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/06/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2024
Type: Wood Frame
Result: Partial Inspection
Status: Issued
Date: 05/16/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/14/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/14/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/13/2024
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 05/17/2024
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 05/14/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/14/2024
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2024
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/16/2024
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/15/2024
Type: Insulation
Result: Partial Inspection
Status: Issued
Date: 05/13/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
MID CONSTRUCTION GROUP

License number: 1030925
Type: B
Phone: Speak with a Permit Expert
Location: LOS ANGELES, CA

Permit Applicant

Principal: TYREE DESEAN BURNETT

Type:

Address: 7136 HASKELL AVE, 320, VAN NUYS CA

Phone:

Experience: years

Applicant: .