Bldg-New Permit

PCIS Permit#: 18010-10000-03872

Address: 6517 LEXINGTON, Los Angeles, 90038

Status: CofO Issued

Status Date: 12/06/2021

Tract: TR 3539

Property Identifier: Block: , Lot: 31, Zone: RD1.5-1XL

Assessor Information: Book: 5533, Page: 1, Parcel: 55

Census Tract: 1908.02

Work Description

PDPP - SMALL LOT SUBDIVISION - SINGLE FAMILY DWELLING WITH ATTACHED GA

Inspection Activity
Date: 12/21/2020
Type: Green Building Rough
Result: Conditional Approval
Status: Issued
Date: 12/21/2020
Type: Verify Sprinkler Sign Off
Result: Corrections Issued
Status: Issued
Date: 12/21/2020
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 12/31/2020
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 12/31/2020
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 12/31/2020
Type: Verify Sprinkler Sign Off
Result: Corrections Issued
Status: Issued
Date: 05/06/2020
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 01/05/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 01/05/2021
Type: BUILDING-Rough-Frame
Result: Conditional Approval
Status: Issued
Date: 01/05/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/28/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 02/25/2020
Type: Underground Mechanical
Result: Approved
Status: Issued
Date: 06/03/2020
Type: Green Building Rough
Result: Conditional Approval
Status: Issued
Date: 06/03/2020
Type: Drywall Nailing
Result: Conditional Approval
Status: Issued
Date: 09/17/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 09/18/2020
Type: Deputy Wood Construction
Result: No Access for Inspection
Status: Issued
Date: 06/10/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/19/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/25/2020
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 06/25/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/06/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/14/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/21/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/21/2020
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 07/24/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 09/30/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/31/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/29/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 01/20/2021
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 01/22/2021
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 01/22/2021
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 01/22/2021
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 08/07/2020
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 08/07/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 01/22/2021
Type: Insulation
Result: Approved
Status: Issued
Date: 01/20/2021
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 01/20/2021
Type: Insulation
Result: Corrections Issued
Status: Issued
Date: 01/20/2021
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 08/11/2020
Type: Verify Sprinkler Sign Off
Result: Partial Approval
Status: Issued
Date: 08/11/2020
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 01/29/2021
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/27/2020
Type: HVAC-Rough
Result: Corrections Issued
Status: Issued
Date: 02/03/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 02/02/2021
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 02/01/2021
Type: Drywall Nailing
Result: Corrections Issued
Status: Issued
Date: 11/10/2020
Type: Deputy Wood Construction
Result: Approved
Status: Issued
Date: 11/09/2020
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 11/17/2020
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 11/18/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/11/2020
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 12/18/2020
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 12/03/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/03/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 03/18/2021
Type: Interior/Exterior Lathing
Result: Corrections Issued
Status: Issued
Date: 03/19/2021
Type: Shower Pan
Result: Approved
Status: Issued
Date: 03/26/2021
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 12/02/2021
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 12/02/2021
Type: HVAC-Final
Result: Approved
Status: CofO in Progress
Date: 12/02/2021
Type: PLUMBING-Final
Result: Approved
Status: CofO in Progress
Date: 09/01/2021
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 06/15/2021
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 12/06/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 06/28/2021
Type: Underground Mechanical
Result: Approved
Status: Issued
Date: 12/06/2021
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 12/06/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 09/21/2021
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 09/28/2021
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 10/01/2021
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 09/30/2021
Type: PLUMBING-Final
Result: Corrections Issued
Status: Issued
Date: 10/08/2021
Type: PLUMBING-Final
Result: Corrections Issued
Status: Issued
Date: 10/07/2021
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 10/04/2021
Type: Gas Test
Result: Approved
Status: Issued
Date: 10/07/2021
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
RAIMONDO CONSTRUCTION COMPANY

License number: 683445
Type: B
Phone: Speak with a Permit Expert
Location: GLENDORA, CA

Permit Applicant

Principal: JOHN RAIMONDO
Type:
Address:
Phone:
Experience: years
Applicant: SAM