Bldg-Alter/Repair Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

Early start permit. Foundation only permit for a new 8-story, 180-unit

Inspection Activity
Date: 10/22/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/24/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/22/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/24/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/21/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/25/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 10/23/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 10/23/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/24/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/23/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/01/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/31/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/29/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 10/29/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 10/28/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/30/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/01/2019
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 03/30/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/15/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 08/13/2019
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 08/16/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 08/14/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/07/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 11/06/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 11/08/2019
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 11/04/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 11/08/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 04/03/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 04/08/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/07/2020
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 04/09/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 08/19/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/21/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 11/22/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/21/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/20/2019
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 08/29/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 08/30/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 08/27/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 08/28/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/22/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 04/17/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/06/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 09/03/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/04/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/03/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/05/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/06/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/05/2019
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 11/25/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 11/25/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 11/26/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/10/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/09/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/13/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 09/12/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/12/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/10/2019
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/16/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/20/2019
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/18/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/17/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/20/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/16/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/02/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/27/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 09/25/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/24/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/24/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 09/25/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 09/23/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 10/04/2019
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/03/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/03/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/01/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/30/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/02/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/01/2019
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 09/30/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/11/2019
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 12/12/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/11/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/07/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/11/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 04/20/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/18/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 10/17/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 10/17/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/16/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 10/15/2019
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 10/16/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 10/18/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 12/16/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/19/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/20/2019
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 12/20/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/17/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/16/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/18/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/19/2019
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 12/23/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/27/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/27/2019
Type: Deputy Shotcrete
Result: Approved
Status: Issued
Date: 12/26/2019
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 12/30/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/31/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 05/08/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/07/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/09/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/08/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/16/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/15/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/15/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/13/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 01/14/2020
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 01/17/2020
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 01/14/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/14/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/12/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/15/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 01/23/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/24/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 01/21/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/21/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/11/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/13/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 09/11/2020
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 01/27/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/31/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 02/07/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 02/13/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/21/2020
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 02/19/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 02/20/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/18/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/27/2020
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 03/03/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/09/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 03/17/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 01/14/2021
Type: Inspection
Result: Permit Finaled
Status: Permit Finaled
Date: 08/07/2020
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 08/13/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
HANOVER R S CONSTRUCTION LLC

License number: 970389
Type: B
Phone: Speak with a Permit Expert
Location: HOUSTON, TX

Permit Applicant

Principal: TIMOTHY CARL BOLTON

Type:

Address: 5847 SAN FELIPE, #3600, HOUSTON, TX

Phone:

Experience: years

Applicant: BRENT MULLINAX