Bldg-New Permit

PCIS Permit#: 18010-20000-02384

Address: 22135 ROSCOE, Los Angeles, 91304

Status: CofO Issued

Status Date: 03/13/2020

Tract: TR 24545

Property Identifier: Block: , Lot: LT 1, Zone: (T)(Q)C2-1

Assessor Information: Book: 2010, Page: 23, Parcel: 20

Census Tract: 1132.32

Work Description

(N) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOU

Inspection Activity
Date: 05/29/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/12/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/13/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 06/17/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/12/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/13/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 07/03/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 07/08/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 11/05/2019
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 07/15/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 07/19/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 11/05/2019
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 11/05/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 11/07/2019
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 07/29/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 11/13/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 11/14/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 11/20/2019
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 11/20/2019
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 11/21/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 11/20/2019
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 11/25/2019
Type: Insulation
Result: Cancelled
Status: Issued
Date: 12/02/2019
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 12/03/2019
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 03/14/2019
Type: Underground Mechanical
Result: Insp Scheduled
Status: Issued
Date: 03/15/2019
Type: Elevator Verification
Result: Not Applicable
Status: Issued
Date: 03/14/2019
Type: Sewer
Result: Insp Scheduled
Status: Issued
Date: 04/05/2019
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 12/19/2019
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 12/23/2019
Type: Shower Pan
Result: Approved
Status: Issued
Date: 05/17/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Shower Pan
Result: Approved
Status: Issued
Date: 01/02/2020
Type: Gas Test
Result: Approved
Status: Issued
Date: 05/23/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 01/24/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 01/21/2020
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 01/24/2020
Type: Service/Power Release
Result: Insp Scheduled
Status: Issued
Date: 01/21/2020
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 02/11/2020
Type: PLUMBING-Final
Result: Approved
Status: Issued
Date: 02/27/2020
Type: Grading Verification
Result: OK for CofO
Status: Issued
Date: 03/06/2020
Type: HVAC-Final
Result: Insp Scheduled
Status: Issued
Date: 03/06/2020
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: Issued
Date: 03/06/2020
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 03/12/2020
Type: Final
Result: OK to Issue CofO
Status: CofO Issued
Date: 03/12/2020
Type: Green Building Final
Result: Approved
Status: CofO Issued
Date: 03/13/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 03/13/2020
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Date: 03/13/2020
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 03/13/2020
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
W C DEVELOPMENT SERVICES INC

License number: 927003
Type: B
Phone: Speak with a Permit Expert
Location: SANTA MONICA, CA

Permit Applicant

Principal: MICHAEL WILLIAM REAMS
Type:
Address: 2716 OCEAN PARK BLVD, #2025, SANTA MONICA, CA
Phone:
Experience: years
Applicant: DEREK SPALDING