Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.

Inspection Activity
Date: 10/22/2019
Type: FLOOD-Elevation Certificate
Result: Not Ready for Inspection
Status: Issued
Date: 10/22/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 10/22/2019
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 10/28/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 11/01/2019
Type: Public Counter
Result: Completed
Status: Issued
Date: 07/22/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/17/2020
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 04/16/2020
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 12/02/2019
Type: FLOOD-Elevation Certificate
Result: Approved
Status: Issued
Date: 12/02/2019
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 12/02/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 10/01/2019
Type: Sewer
Result: Corrections Issued
Status: Issued
Date: 12/13/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 12/11/2019
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 12/11/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 10/07/2019
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 10/07/2019
Type: Sewer
Result: Partial Approval
Status: Issued
Date: 04/19/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/17/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 10/17/2019
Type: FLOOD-Elevation Certificate
Result: Not Ready for Inspection
Status: Issued
Date: 10/18/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 10/17/2019
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/28/2020
Type: Rough-Elec/Plmb/HVAC
Result: Insp Cancelled
Status: Issued
Date: 05/06/2019
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 12/23/2019
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 12/24/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 12/23/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 05/07/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/05/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/04/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 04/19/2021
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 09/08/2020
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/07/2020
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 01/04/2021
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 01/04/2021
Type: Rough-Elec/Plmb/HVAC
Result: Partial Approval
Status: Issued
Date: 01/08/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/08/2021
Type: Rough-Elec/Plmb/HVAC
Result: Partial Approval
Status: Issued
Date: 01/08/2021
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 01/04/2021
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 06/03/2020
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 06/03/2020
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/03/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 08/11/2021
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 08/12/2021
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 09/22/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 09/22/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/22/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 06/26/2020
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 09/22/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 07/06/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/22/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/22/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 07/21/2020
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 07/28/2020
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 07/28/2020
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 07/28/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 07/28/2020
Type: FLOOD-Proofing Certificate
Result: Approved
Status: Issued
Date: 10/06/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 10/29/2020
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 10/29/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 10/29/2020
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 05/06/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 11/23/2020
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 11/23/2020
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 11/23/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 11/23/2020
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/23/2020
Type: Rough-Elec/Plmb/HVAC
Result: Partial Approval
Status: Issued
Date: 08/17/2021
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 08/17/2021
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 08/17/2021
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 08/20/2021
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 08/20/2021
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 05/13/2021
Type: Interior/Exterior Lathing
Result: Corrections Issued
Status: Issued
Date: 05/11/2021
Type: Interior/Exterior Lathing
Result: No Access for Inspection
Status: Issued
Date: 12/16/2020
Type: Rough-Elec/Plmb/HVAC
Result: Not Ready for Inspection
Status: Issued
Date: 12/16/2020
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 05/18/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 08/25/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 03/19/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/19/2021
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/25/2021
Type: Interior/Exterior Lathing
Result: Corrections Issued
Status: Issued
Date: 03/23/2021
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/23/2021
Type: ELECTRICAL-Rough
Result: Corrections Issued
Status: Issued
Date: 03/26/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 05/25/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/02/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 04/12/2021
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/12/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/13/2021
Type: PLUMBING-Rough
Result: Insp Cancelled
Status: Issued
Date: 04/12/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 04/13/2021
Type: HVAC-Rough
Result: Insp Cancelled
Status: Issued
Date: 04/13/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/10/2021
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 06/08/2021
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/15/2021
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 06/17/2021
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/08/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/08/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/29/2021
Type: HVAC-Rough
Result: Corrections Issued
Status: Issued
Date: 09/17/2021
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/14/2021
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 07/23/2021
Type: ELECTRICAL-Rough
Result: Corrections Issued
Status: Issued
Date: 07/29/2021
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/15/2021
Type: Wood Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/15/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 08/04/2021
Type: HVAC-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/04/2021
Type: ELECTRICAL-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/27/2021
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 09/01/2022
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 09/01/2022
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 09/01/2022
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 11/16/2021
Type: Shower Pan
Result: Not Ready for Inspection
Status: Issued
Date: 11/16/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/16/2021
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 11/19/2021
Type: Shower Pan
Result: Approved
Status: Issued
Date: 01/27/2022
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 09/01/2022
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/01/2022
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/18/2022
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 02/18/2022
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 04/08/2022
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 04/08/2022
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/08/2022
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 04/10/2023
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/10/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 07/08/2022
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 07/12/2022
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 05/27/2022
Type: Insulation
Result: Approved
Status: Issued
Date: 05/24/2022
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 05/24/2022
Type: Insulation
Result: Corrections Issued
Status: Issued
Date: 12/30/2022
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 12/29/2022
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 12/29/2022
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 07/25/2022
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 08/03/2022
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 08/09/2022
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 09/27/2022
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 08/15/2022
Type: Service/Power Release
Result: Corrections Issued
Status: Issued
Date: 01/03/2023
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 01/03/2023
Type: Elevator Verification
Result: Not Applicable
Status: Issued
Date: 08/22/2022
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 08/23/2022
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 08/26/2022
Type: Service/Power Release
Result: Approved
Status: Issued
Date: 08/25/2022
Type: Service/Power Release
Result: Corrections Issued
Status: Issued
Date: 10/03/2022
Type: Grading Pre-Inspection
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2022
Type: Final
Result: Corrections Issued
Status: Issued
Date: 10/06/2022
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2022
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 10/06/2022
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 01/25/2023
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 01/25/2023
Type: Green Building Final
Result: Approved
Status: Issued
Date: 01/25/2023
Type: HVAC-Final
Result: Corrections Issued
Status: Issued
Date: 01/25/2023
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 01/25/2023
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 01/25/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 01/30/2023
Type: Pre-Inspection
Result: Cancelled
Status: Issued
Date: 08/28/2023
Type: HVAC-Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/28/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 08/28/2023
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 08/28/2023
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/04/2023
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/04/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 12/18/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 12/18/2023
Type: Final
Result: Corrections Issued
Status: Issued
Date: 01/30/2024
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 02/09/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/09/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/12/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/13/2024
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 02/12/2024
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/27/2024
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 02/27/2024
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 02/29/2024
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/27/2024
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/13/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 03/19/2024
Type: Wood Frame
Result: Corrections Issued
Status: Issued
Date: 03/26/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 03/29/2024
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 03/26/2024
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 03/26/2024
Type: Grading Verification
Result: OK for CofO
Status: Issued
Date: 03/29/2024
Type: HVAC-Final
Result: Partial Approval
Status: Issued
Date: 03/27/2024
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 04/03/2024
Type: ELECTRICAL-Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/03/2024
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 04/03/2024
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/05/2024
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 04/04/2024
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 04/03/2024
Type: PLUMBING-Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/04/2024
Type: PLUMBING-Final
Result: Corrections Issued
Status: Issued
Date: 04/08/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 04/08/2024
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Date: 04/08/2024
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 04/08/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
SILVERSTON & ASSOCIATES INC

License number: 488695
Type: B
Phone: Speak with a Permit Expert
Location: MALIBU, CA

Permit Applicant

Principal: GARY STEFEN SILVERSTON

Type:

Address: -, -, -

Phone:

Experience: years

Applicant: GARY SILVERSTON