Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

TI TO (E) BUILDING. CONVERT BASEMENT TO NEW OFFICE AREA, FIRST FLOOR T

Inspection Activity
Date: 07/19/2018
Type: Deputy Grading
Result: Insp Cancelled
Status: Issued
Date: 07/20/2018
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 07/20/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 07/19/2018
Type: Deputy Grading
Result: No Access for Inspection
Status: Issued
Date: 07/20/2018
Type: Deputy Grading
Result: Insp Cancelled
Status: Issued
Date: 07/26/2018
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 07/23/2018
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 07/23/2018
Type: Deputy Grading
Result: Partial Approval
Status: Issued
Date: 07/23/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 07/24/2018
Type: Deputy Grading
Result: Partial Approval
Status: Issued
Date: 07/27/2018
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 07/26/2018
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 07/27/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/30/2018
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 07/31/2018
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 07/30/2018
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 07/31/2018
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 08/13/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/13/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/23/2018
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 08/30/2018
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/27/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 09/07/2018
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 09/04/2018
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 09/12/2018
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 09/12/2018
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/10/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 09/14/2018
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 09/12/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 09/12/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 09/24/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/04/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/05/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/01/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/03/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/09/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/10/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/09/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/10/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/11/2018
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 12/22/2020
Type: Plumbing Verification
Result: CofO on Hold
Status: Issued
Date: 10/17/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/15/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/17/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/19/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/15/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/19/2018
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 10/18/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/16/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/16/2018
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 10/15/2018
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 10/24/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/24/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/25/2018
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 10/26/2018
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 11/08/2018
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 11/09/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/24/2018
Type: Light Gage Steel Frame
Result: No Access for Inspection
Status: Issued
Date: 01/02/2019
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 01/04/2019
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 01/11/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/07/2019
Type: Deputy Drilled-In Anchors
Result: Partial Approval
Status: Issued
Date: 01/24/2019
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 09/18/2019
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 09/19/2019
Type: Plumbing Verification
Result: Insp Scheduled
Status: Issued
Date: 09/19/2019
Type: Fire Sprinkler Verification
Result: OK for CofO
Status: Issued
Date: 09/18/2019
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 09/19/2019
Type: Electrical Verification
Result: OK for CofO
Status: Issued
Date: 09/19/2019
Type: Final
Result: Partial Inspection
Status: Issued
Date: 09/18/2019
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 09/18/2019
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/19/2019
Type: Grading Verification
Result: CofO on Hold
Status: Issued
Date: 09/18/2019
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 09/18/2019
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/18/2019
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 09/19/2019
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: Issued
Date: 09/18/2019
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 02/20/2019
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/01/2019
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 01/22/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/22/2021
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 01/19/2021
Type: Final
Result: Conditional Approval
Status: CofO Issued
Date: 01/22/2021
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/19/2021
Type: Green Building Final
Result: Approved
Status: CofO Issued
Date: 01/21/2021
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Date: 01/21/2021
Type: Inspection
Result: OK for CofO
Status: CofO Issued
Date: 01/19/2021
Type: Smoke Detectors
Result: Approved
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
PINNACLE CONTRACTING CORPORATION

License number: 665647
Type: B
Phone: Speak with a Permit Expert
Location: WOODLAND HILLS, CA

Permit Applicant

Principal: JAMES MICHAEL GROSSMAN

Type:

Address: 453 S. SPRING ST., #508, LA, CA

Phone:

Experience: years

Applicant: NORA GORDON