Bldg-Alter/Repair Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

SUPPLEMENTAL PERMIT TO 18016-10000-03811 FOR STRUCTURAL RETROFIT OF (E

Inspection Activity
Date: 05/29/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/31/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/30/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/10/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/11/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/13/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/14/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/12/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/01/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/30/2018
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/31/2018
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/31/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/30/2018
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/20/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/18/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/19/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/17/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/10/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/11/2019
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/20/2018
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 06/14/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/12/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/13/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/29/2018
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/29/2018
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 07/02/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 07/03/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/05/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/03/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 07/02/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/12/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/11/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/12/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/10/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/10/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/12/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/12/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/11/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/18/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/18/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/16/2018
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 07/16/2018
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 07/16/2018
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 07/18/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/18/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 07/17/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/17/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/17/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/20/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 07/18/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/20/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/20/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/16/2018
Type: T-Bar Ceiling
Result: Not Ready for Inspection
Status: Issued
Date: 07/17/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/20/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/17/2018
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 07/11/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 07/23/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 07/27/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 08/02/2018
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: T-Bar Ceiling
Result: Not Ready for Inspection
Status: Issued
Date: 08/02/2018
Type: Insulation
Result: Not Ready for Inspection
Status: Issued
Date: 08/10/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 08/10/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 08/10/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 08/10/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 08/17/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 08/17/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 08/17/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 08/17/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 07/26/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 07/26/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/22/2019
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/24/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 07/23/2019
Type: Deputy Fireproofing
Result: Approved
Status: Issued
Date: 07/23/2019
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/22/2019
Type: Deputy Fireproofing
Result: Approved
Status: Issued
Date: 07/25/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/25/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 07/24/2019
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 08/31/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 09/05/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 09/11/2018
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/25/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 09/25/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 09/27/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 09/27/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 09/25/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 09/27/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 09/25/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 09/27/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 10/01/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/01/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/04/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/04/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/01/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/04/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/12/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 10/11/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/11/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 10/12/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/11/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/10/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/11/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 10/12/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/12/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/24/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/25/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/24/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 10/24/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/25/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 10/25/2018
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 10/25/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 10/25/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 11/05/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 11/05/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 11/07/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 11/09/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 11/05/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 11/05/2018
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 11/07/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 11/09/2018
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 11/07/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 11/07/2018
Type: Insulation
Result: Insp Scheduled
Status: Issued
Date: 11/09/2018
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/08/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/10/2019
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/08/2019
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/10/2019
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 01/10/2019
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 01/18/2019
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 01/16/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 01/16/2019
Type: Deputy Fireproofing
Result: Conditional Approval
Status: Issued
Date: 01/14/2019
Type: Deputy Fireproofing
Result: Conditional Approval
Status: Issued
Date: 01/16/2019
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/15/2019
Type: Deputy Fireproofing
Result: Conditional Approval
Status: Issued
Date: 01/17/2019
Type: Deputy Fireproofing
Result: Conditional Approval
Status: Issued
Date: 01/25/2019
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 01/25/2019
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 01/25/2019
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 02/05/2019
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/21/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 02/22/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 02/25/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 03/14/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 03/20/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 03/21/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 04/03/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 04/06/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Pending Review
Status: Issued
Date: 04/06/2019
Type: Footing/Foundation/Slab
Result: Off-Hour Fees Due
Status: Issued
Date: 04/09/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 04/24/2019
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/16/2019
Type: Final
Result: Permit Finaled
Status: Permit Finaled
Date: 05/02/2019
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 05/03/2019
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 12/16/2019
Type: Smoke Detectors
Result: Approved
Status: Permit Finaled
Date: 05/08/2019
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 05/13/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/15/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 05/22/2019
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
SATTERFIELD & PONTIKES / STV JV - STV CONSTRUCTION, INC

License number: 1022839
Type: B
Phone: Speak with a Permit Expert
Location: HOUSTON, TX

Permit Applicant

Principal: STEVEN JAMES PRESSLER

Type:

Address: 241 S. FIGUEROA ST, SUITE 370, LOS ANGELES, CA

Phone:

Experience: years

Applicant: KIMBERLINA WHETTAM