HVAC Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

GENERAL HVAC FOR 6 STORY, 60 UNIT APARTMENT BUILDING OVER UNDERGROUND

Inspection Activity
Date: 04/20/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 08/09/2021
Type: Green HVAC Rough
Result: Partial Inspection
Status: Issued
Date: 08/09/2021
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 04/26/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 05/05/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 05/11/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 08/27/2021
Type: Rough-A/C and Heating
Result: Insp Scheduled
Status: Issued
Date: 08/27/2021
Type: Green HVAC Rough
Result: Insp Scheduled
Status: Issued
Date: 04/15/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 04/15/2021
Type: Green HVAC Rough
Result: Partial Inspection
Status: Issued
Date: 06/24/2021
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 06/24/2021
Type: Green HVAC Rough
Result: Partial Approval
Status: Issued
Date: 07/02/2021
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 07/02/2021
Type: Green HVAC Rough
Result: Partial Approval
Status: Issued
Date: 07/09/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 07/09/2021
Type: Green HVAC Rough
Result: Partial Approval
Status: Issued
Date: 07/19/2021
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 09/29/2021
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 10/26/2021
Type: Fire Damper Framing
Result: Partial Approval
Status: Issued
Date: 10/25/2021
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 01/19/2022
Type: Rough-Ventilation
Result: Partial Inspection
Status: Issued
Date: 08/31/2022
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 01/28/2022
Type: Rough-Ventilation
Result: Partial Inspection
Status: Issued
Date: 04/14/2023
Type: Rough-Ventilation
Result: Insp Scheduled
Status: Issued
Date: 07/06/2022
Type: Rough-Ventilation
Result: Partial Approval
Status: Issued
Date: 04/14/2023
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 07/22/2022
Type: Fire Damper Framing
Result: Insp Scheduled
Status: Issued
Date: 08/04/2022
Type: Rough-Ventilation
Result: Corrections Issued
Status: Issued
Date: 08/10/2022
Type: Rough-A/C and Heating
Result: Partial Approval
Status: Issued
Date: 01/06/2023
Type: Rough-A/C and Heating
Result: Insp Scheduled
Status: Issued
Date: 12/08/2022
Type: Rough-Ventilation
Result: Corrections Issued
Status: Issued
Date: 03/30/2023
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 01/17/2024
Type: Special/Order Compliance
Result: Partial Approval
Status: Issued
Date: 03/15/2024
Type: REFRIGERATION-Final
Result: Corrections Issued
Status: Issued
Date: 03/13/2024
Type: VENTILATION-Final
Result: Partial Approval
Status: Issued
Date: 03/14/2024
Type: HEATING-Final
Result: Partial Approval
Status: Issued
Date: 03/20/2024
Type: Rough-A/C and Heating
Result: Partial Inspection
Status: Issued
Date: 03/18/2024
Type: VENTILATION-Final
Result: Partial Inspection
Status: Issued
Date: 03/19/2024
Type: HEATING-Final
Result: Partial Approval
Status: Issued
Date: 03/20/2024
Type: Green HVAC Final
Result: No Access for Inspection
Status: Issued
Date: 03/21/2024
Type: VENTILATION-Final
Result: Corrections Issued
Status: Issued
Date: 03/20/2024
Type: Final
Result: Partial Inspection
Status: Issued
Date: 03/27/2024
Type: Test-Life Sfty/Vent/Smoke/Air
Result: Partial Approval
Status: Issued
Date: 03/27/2024
Type: VENTILATION-Final
Result: Partial Inspection
Status: Issued
Date: 03/28/2024
Type: HEATING-Final
Result: Insp Cancelled
Status: Issued
Date: 04/05/2024
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 04/02/2024
Type: HEATING-Final
Result: Partial Approval
Status: Issued
Date: 04/04/2024
Type: Final
Result: Partial Inspection
Status: Issued
Date: 04/05/2024
Type: Green HVAC Final
Result: Insp Scheduled
Status: Issued
Date: 04/05/2024
Type: Rough-A/C and Heating
Result: Insp Scheduled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
MANDAC INC

License number: 421428
Type: C20
Phone: Speak with a Permit Expert
Location: BURBANK, CA

Permit Applicant

Principal: DANE ANTHONY FRANK

Type:

Address: 3 MACARTHUR PL, SANTA ANA, CA

Phone:

Experience: years

Applicant: FRANK NGUYEN