Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW 4 STORY, TYPE IIA, UNDERGRADUATE BUILDING WITH PRIMARILY CLASSROOM

Inspection Activity
Date: 12/22/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 08/21/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/21/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/21/2020
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 04/02/2020
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 04/02/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 08/27/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/27/2020
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 08/28/2020
Type: Piling/Pier/Caisson
Result: Insp Scheduled
Status: Issued
Date: 08/25/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/25/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/24/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 08/26/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/26/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/27/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/26/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 08/25/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 04/24/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 04/23/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 04/24/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 04/19/2021
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 04/29/2020
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 04/29/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/29/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/30/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/27/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 04/29/2020
Type: METHANE-Barrier
Result: Partial Approval
Status: Issued
Date: 05/08/2020
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 05/12/2020
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/12/2020
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 05/13/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 05/12/2020
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 05/12/2020
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 05/14/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/15/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/22/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 02/06/2020
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 01/07/2021
Type: Interior/Exterior Lathing
Result: Order to Comply Issued
Status: Issued
Date: 01/07/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/11/2020
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 05/28/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 05/29/2020
Type: Deputy Methane Barrier
Result: Insp Scheduled
Status: Issued
Date: 09/18/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 09/18/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 09/17/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/02/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/01/2020
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2020
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2020
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 06/11/2020
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 06/11/2020
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 06/10/2020
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/10/2020
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/12/2020
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 06/11/2020
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 06/12/2020
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 09/25/2020
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 06/18/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/18/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 06/18/2020
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 06/18/2020
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 06/19/2020
Type: Deputy Methane Barrier
Result: Conditional Approval
Status: Issued
Date: 09/25/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/21/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 09/24/2020
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 09/21/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 01/12/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 01/11/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/23/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 06/22/2020
Type: Deputy Methane Barrier
Result: Approved
Status: Issued
Date: 06/22/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 01/11/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/14/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 01/11/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 07/10/2020
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/25/2020
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/25/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/21/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 09/24/2020
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 09/21/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/13/2020
Type: Deputy Other (see comments)
Result: Approved
Status: Issued
Date: 07/23/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/24/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/24/2020
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/24/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 07/23/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/28/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/27/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/27/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/31/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/30/2020
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 07/28/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/30/2020
Type: Reinforced Concrete Frame
Result: Partial Inspection
Status: Issued
Date: 01/19/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 01/22/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 08/07/2020
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/07/2020
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 01/22/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 01/19/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 10/13/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 01/22/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 08/11/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/12/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/12/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/10/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/10/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 08/11/2020
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 10/08/2020
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/16/2020
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 01/26/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 10/26/2020
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 10/28/2020
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 02/03/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/01/2021
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 02/01/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/05/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/03/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/03/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 11/12/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 02/10/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 11/19/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/18/2020
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 02/12/2021
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 02/08/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 11/24/2020
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 11/23/2020
Type: Light Gage Steel Frame
Result: Partial Inspection
Status: Issued
Date: 02/16/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 12/01/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 12/04/2020
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 02/16/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/18/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/16/2021
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/08/2020
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 12/08/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 12/18/2020
Type: Interior/Exterior Lathing
Result: Insp Scheduled
Status: Issued
Date: 12/15/2020
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 12/17/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/25/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 02/26/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 03/02/2021
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 03/04/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 03/12/2021
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 03/10/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 03/11/2021
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/16/2021
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 03/16/2021
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 03/15/2021
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 03/24/2021
Type: T-Bar Ceiling
Result: Partial Approval
Status: Issued
Date: 04/09/2021
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 04/13/2021
Type: T-Bar Ceiling
Result: Partial Approval
Status: Issued
Date: 06/09/2021
Type: Green Building Final
Result: Approved
Status: Issued
Date: 06/09/2021
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 06/09/2021
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 06/09/2021
Type: Final
Result: Partial Inspection
Status: Issued
Date: 06/09/2021
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 06/09/2021
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 06/09/2021
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 07/02/2021
Type: Fire Sprinkler Verification
Result: CofO on Hold
Status: Issued
Date: 07/01/2021
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 07/02/2021
Type: Heat,Vent,A/C Verification
Result: Insp Scheduled
Status: Issued
Date: 07/02/2021
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 07/02/2021
Type: Grading Verification
Result: Insp Scheduled
Status: Issued
Date: 07/02/2021
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 07/02/2021
Type: Pressure Vessel Verification
Result: Insp Scheduled
Status: Issued
Date: 07/02/2021
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 07/08/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/09/2021
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/09/2021
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 07/07/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/06/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/06/2021
Type: Pre-Inspection
Result: Partial Approval
Status: Issued
Date: 07/07/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/06/2021
Type: Elevator Verification
Result: OK for CofO
Status: Issued
Date: 07/14/2021
Type: TCO Electrical Verification
Result: Completed (special insp)
Status: Issued
Date: 07/14/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/16/2021
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/13/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/12/2021
Type: T-Bar Ceiling
Result: Approved
Status: Issued
Date: 07/15/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 07/19/2021
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 12/15/2021
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 06/15/2022
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 01/27/2023
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 01/25/2023
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 01/26/2023
Type: Grading Verification
Result: Not Applicable
Status: Issued
Date: 07/06/2023
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 01/03/2024
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 01/31/2024
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 01/31/2024
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 01/31/2024
Type: Electrical Verification
Result: Cancelled
Status: CofO in Progress
Date: 02/12/2024
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 02/12/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 02/12/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
O'NEIL W E CONSTRUCTION CO OF CALIFORNIA

License number: 494031
Type: B
Phone: Speak with a Permit Expert
Location: EL SEGUNDO, CA

Permit Applicant

Principal: JOHN EDWARD FINN

Type:

Address:

Phone:

Experience: years

Applicant: FRANCO LEMUS