Bldg-New Permit

PCIS Permit#: 19010-10000-06105

Address: 15640 ROSCOE, Los Angeles, 91406

Status: CofO Issued

Status Date: 09/28/2022

Tract: TR 1000

Property Identifier: Block: , Lot: 428, Zone: M2-1

Assessor Information: Book: 2673, Page: 22, Parcel: 36

Census Tract: 1274

Work Description

PROPOSED SELF STORAGE BUILDING

Inspection Activity
Date: 11/24/2021
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 04/21/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/23/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/19/2021
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/23/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/22/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/19/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/21/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/20/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/20/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/20/2021
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 04/20/2021
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 04/21/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/23/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/23/2021
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/23/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 04/23/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/21/2021
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 04/20/2021
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 04/22/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/22/2021
Type: Masonry Wall/Backfill
Result: Insp Cancelled
Status: Issued
Date: 08/09/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 08/11/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/09/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/12/2021
Type: Reinforced Masonry Frame
Result: Cancelled
Status: Issued
Date: 08/11/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/27/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/29/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/28/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 04/29/2021
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/30/2021
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/28/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 04/27/2021
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/29/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/27/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/28/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/26/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/26/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/30/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/30/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/05/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/03/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/08/2021
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/06/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/05/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/05/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/04/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/04/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/03/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/07/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/06/2021
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 05/07/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/06/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/04/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/06/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/04/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/07/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/06/2021
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 05/07/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/03/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/03/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 05/03/2021
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 05/06/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 05/05/2021
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/06/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/20/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 08/17/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 08/20/2021
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 08/17/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/13/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/14/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/11/2021
Type: Green Building Rough
Result: Cancelled
Status: Issued
Date: 05/13/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/14/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/11/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/12/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/10/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/14/2021
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/11/2021
Type: Reinforced Concrete Frame
Result: Cancelled
Status: Issued
Date: 05/12/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/11/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/10/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 02/22/2021
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 12/03/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/19/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/17/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/18/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 03/03/2021
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/05/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/21/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/18/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/19/2021
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 05/20/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/19/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/20/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 05/21/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/21/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 05/20/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/18/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/17/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/19/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 03/08/2021
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 03/12/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 12/03/2021
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 08/27/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/25/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 08/26/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/23/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/24/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 08/26/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/27/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 03/18/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/19/2021
Type: Verify Sprinkler Sign Off
Result: Insp Scheduled
Status: Issued
Date: 03/18/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 03/18/2021
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 03/19/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 03/19/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 03/17/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 08/24/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/23/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/28/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/26/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/26/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/27/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/26/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/25/2021
Type: Deputy Reinf. Masonry
Result: Insp Cancelled
Status: Issued
Date: 05/26/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 05/28/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 05/26/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 03/23/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 03/24/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/26/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 03/26/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 05/27/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/25/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/26/2021
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/28/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/28/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 05/26/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/25/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/25/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/25/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 03/31/2021
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/03/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 06/01/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/03/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/02/2021
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 06/02/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 06/03/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 06/03/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 06/04/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/04/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/03/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 04/09/2021
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 04/05/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/07/2021
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 04/05/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 04/07/2021
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 04/07/2021
Type: Reinforced Concrete Frame
Result: Corrections Issued
Status: Issued
Date: 04/05/2021
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 04/09/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 04/06/2021
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/03/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/02/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/01/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 06/02/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 02/28/2022
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 03/03/2022
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 04/17/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 04/13/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/15/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/15/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/14/2021
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 04/15/2021
Type: Verify Sprinkler Sign Off
Result: Not Ready for Inspection
Status: Issued
Date: 04/15/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/13/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/13/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/01/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/03/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 08/31/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/30/2021
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/07/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/08/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/08/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/07/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/02/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/03/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/02/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/31/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/03/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 09/03/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/01/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/16/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/18/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/16/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/17/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/15/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/17/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 06/17/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 06/17/2021
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 06/15/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/18/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/15/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/14/2021
Type: Green Building Rough
Result: Partial Approval
Status: Issued
Date: 06/17/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/16/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/18/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/14/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 09/08/2021
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 09/07/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/25/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/22/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/23/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/23/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/22/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/24/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/25/2021
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 06/23/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/25/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/21/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/25/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/25/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/21/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/22/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/24/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/24/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/21/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/07/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 09/10/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/10/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/09/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/09/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/06/2021
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/09/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 06/28/2021
Type: Deputy Reinf. Concrete
Result: No Access for Inspection
Status: Issued
Date: 07/01/2021
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 06/29/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 07/02/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/29/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/28/2021
Type: Deputy Reinf. Masonry
Result: No Access for Inspection
Status: Issued
Date: 07/01/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/30/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/30/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/30/2021
Type: Green Building Rough
Result: Cancelled
Status: Issued
Date: 07/02/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/01/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/01/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/01/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 06/29/2021
Type: Reinforced Concrete Frame
Result: Cancelled
Status: Issued
Date: 07/01/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/28/2021
Type: Deputy Pre-Stress Concrete
Result: No Access for Inspection
Status: Issued
Date: 07/02/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 06/29/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 12/09/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/14/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/13/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/16/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 07/08/2021
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 07/09/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 07/07/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 07/08/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/07/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/07/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/08/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 07/09/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/09/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 07/08/2021
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 07/08/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/17/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/15/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/14/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/17/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/15/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/17/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/15/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/13/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/15/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 09/16/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/12/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 07/16/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/12/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 07/13/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/15/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/16/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/14/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/14/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/13/2021
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 07/15/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 07/15/2021
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 07/14/2021
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 07/13/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 07/16/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/12/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/14/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/13/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 07/21/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 07/20/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 07/20/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 07/19/2021
Type: Deputy Drilled-In Anchors
Result: Approved
Status: Issued
Date: 07/21/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 07/19/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/19/2021
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 09/23/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/22/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/20/2021
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 09/22/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 09/20/2021
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/30/2021
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/29/2021
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 07/30/2021
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 07/30/2021
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 09/22/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 08/06/2021
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 08/06/2021
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/29/2021
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 09/29/2021
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 09/29/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 09/29/2021
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 03/11/2022
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/07/2021
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/06/2021
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/07/2021
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
DAI GENERAL CONTRACTING

License number: 861151
Type: B
Phone: Speak with a Permit Expert
Location: IRVINE, CA

Permit Applicant

Principal: LAURENCE HALL DAMATO
Type:
Address: 5635 EVENING SKY DR, SIMI VALLEY, CA
Phone:
Experience: years
Applicant: TERRI DICKERHOFF