Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

(N) SFD 2-STORY WITH ATTACHED GARAGE

Inspection Activity
Date: 09/02/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/31/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 08/30/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 09/01/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 09/02/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 06/21/2022
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 12/20/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/15/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/12/2022
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 06/02/2022
Type: Pre-Inspection
Result: Approved
Status: Issued
Date: 08/03/2022
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 08/12/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 08/17/2022
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 08/15/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/16/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 08/15/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 08/26/2022
Type: Deputy Grading
Result: Conditional Approval
Status: Issued
Date: 08/22/2022
Type: Piling/Pier/Caisson
Result: Partial Inspection
Status: Issued
Date: 01/20/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 01/18/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/28/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 10/29/2022
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 11/23/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 11/30/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/28/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 02/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 02/14/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/23/2023
Type: Underground Mechanical
Result: Insp Scheduled
Status: Issued
Date: 04/26/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 04/24/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/26/2023
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 05/23/2024
Type: Shower Pan
Result: Approved
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/08/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/04/2023
Type: Deputy Wood Construction
Result: No Access for Inspection
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/08/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/08/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/10/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 10/12/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/08/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/11/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/10/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/29/2024
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 05/15/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 05/17/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 10/18/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/16/2023
Type: HVAC-Rough
Result: Partial Approval
Status: Issued
Date: 05/23/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/22/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/02/2023
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 10/23/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 06/06/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 06/06/2023
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 06/07/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/15/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/16/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/20/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/20/2023
Type: Deputy Steel/Welding
Result: No Access for Inspection
Status: Issued
Date: 06/20/2023
Type: Deputy Steel/Welding
Result: No Access for Inspection
Status: Issued
Date: 11/02/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/03/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 11/09/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/10/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 07/13/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 11/08/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Approved
Status: Issued
Date: 11/14/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 11/13/2023
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 11/14/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 11/22/2023
Type: BUILDING-Rough-Frame
Result: Insp Cancelled
Status: Issued
Date: 11/22/2023
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 08/09/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 08/08/2023
Type: Deputy Wood Construction
Result: Partial Approval
Status: Issued
Date: 11/22/2023
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 11/22/2023
Type: FLOOD-Proofing Certificate
Result: Insp Cancelled
Status: Issued
Date: 08/17/2023
Type: Sewer
Result: Corrections Issued
Status: Issued
Date: 08/15/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 08/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/15/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Corrections Issued
Status: Issued
Date: 11/29/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 11/27/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 11/27/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 08/23/2023
Type: Sewer
Result: Corrections Issued
Status: Issued
Date: 08/23/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 08/30/2023
Type: Deputy Steel/Welding
Result: No Access for Inspection
Status: Issued
Date: 09/08/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 09/12/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 09/11/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 09/14/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 09/15/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 09/20/2023
Type: Deputy Steel/Welding
Result: Partial Approval
Status: Issued
Date: 09/22/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 12/12/2023
Type: FLOOD-Proofing Certificate
Result: Insp Cancelled
Status: Issued
Date: 12/12/2023
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 12/12/2023
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 12/12/2023
Type: BUILDING-Rough-Frame
Result: Insp Cancelled
Status: Issued
Date: 07/03/2024
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/05/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 02/07/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 02/12/2024
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 02/12/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 02/23/2024
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 02/23/2024
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 02/23/2024
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 02/20/2024
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 02/26/2024
Type: HVAC-Rough
Result: Insp Cancelled
Status: Issued
Date: 03/05/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 03/05/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 03/08/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 03/12/2024
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 04/05/2024
Type: BUILDING-Rough-Frame
Result: Insp Cancelled
Status: Issued
Date: 04/05/2024
Type: FLOOD-Proofing Certificate
Result: Insp Cancelled
Status: Issued
Date: 04/05/2024
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 04/05/2024
Type: Verify Sprinkler Sign Off
Result: Insp Cancelled
Status: Issued
Date: 04/05/2024
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 04/10/2024
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 04/11/2024
Type: Wood Frame
Result: Insp Cancelled
Status: Issued
Date: 04/10/2024
Type: FLOOD-Proofing Certificate
Result: Insp Cancelled
Status: Issued
Date: 04/10/2024
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/10/2024
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 04/10/2024
Type: Wood Frame
Result: Cancelled
Status: Issued
Date: 04/18/2024
Type: Insulation
Result: Approved
Status: Issued
Date: 05/10/2024
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 05/17/2024
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 05/17/2024
Type: Drywall Nailing
Result: Approved
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
N W G C INC

License number: 770243
Type: B
Phone: Speak with a Permit Expert
Location: SANTA MONICA, CA

Permit Applicant

Principal: NATHAN ALAN WASIK

Type:

Address:

Phone:

Experience: years

Applicant: ERIK CONARD