Bldg-Addition Permit

PCIS Permit#: 19014-30000-02569

Address: 4321 WESTLAWN, Los Angeles, 90066

Status: CofO Issued

Status Date: 05/04/2022

Tract: TR 7358

Property Identifier: Block: , Lot: 221, Zone: R1-1

Assessor Information: Book: 4231, Page: 14, Parcel: 20

Census Tract: 2753.11

Work Description

2 STORY ADDITION TO AN (E) 1 STORY SFD WITH A (N) ATTACHED GARAGE

Inspection Activity
Date: 03/23/2020
Type: ELECTRICAL-Final
Result: Approved
Status: Issued
Date: 11/08/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Not Ready for Inspection
Status: Issued
Date: 11/08/2019
Type: Underground Mechanical
Result: Partial Approval
Status: Issued
Date: 04/08/2020
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 04/06/2020
Type: Final
Result: Corrections Issued
Status: CofO in Progress
Date: 11/15/2019
Type: HVAC-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/14/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 04/06/2020
Type: Service/Power Release
Result: Not Ready for Inspection
Status: CofO in Progress
Date: 04/06/2020
Type: Footing/Foundation/Slab
Result: Approved
Status: CofO in Progress
Date: 04/08/2020
Type: Green Building Final
Result: Approved
Status: CofO in Progress
Date: 04/08/2020
Type: Service/Power Release
Result: Approved
Status: CofO in Progress
Date: 04/09/2020
Type: Service/Power Release
Result: Approved
Status: CofO in Progress
Date: 04/08/2020
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 04/06/2020
Type: Smoke Detectors
Result: Approved
Status: CofO in Progress
Date: 04/06/2020
Type: Green Building Final
Result: Not Ready for Inspection
Status: CofO in Progress
Date: 11/22/2019
Type: ELECTRICAL-Rough
Result: Corrections Issued
Status: Issued
Date: 11/18/2019
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 11/22/2019
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 11/20/2019
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 11/20/2019
Type: Deputy Wood Construction
Result: Conditional Approval
Status: Issued
Date: 11/25/2019
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 11/25/2019
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 12/06/2019
Type: HVAC-Rough
Result: Insp Scheduled
Status: Issued
Date: 12/02/2019
Type: Green Building Rough
Result: No Access for Inspection
Status: Issued
Date: 12/02/2019
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 10/04/2019
Type: Underground Mechanical
Result: Insp Scheduled
Status: Issued
Date: 10/04/2019
Type: PLUMBING-Rough
Result: Insp Scheduled
Status: Issued
Date: 10/04/2019
Type: Sewer
Result: Insp Scheduled
Status: Issued
Date: 12/11/2019
Type: Shower Pan
Result: Approved
Status: Issued
Date: 12/11/2019
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/11/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/11/2019
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 10/09/2019
Type: Footing/Foundation/Slab
Result: Conditional Approval
Status: Issued
Date: 10/18/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 12/19/2019
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 12/19/2019
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 12/16/2019
Type: ELECTRICAL-Rough
Result: No Access for Inspection
Status: Issued
Date: 12/19/2019
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 12/16/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: No Access for Inspection
Status: Issued
Date: 12/17/2019
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 12/16/2019
Type: PLUMBING-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 04/29/2020
Type: Service/Power Release
Result: Not Required
Status: CofO in Progress
Date: 12/23/2019
Type: Interior/Exterior Lathing
Result: Partial Approval
Status: Issued
Date: 01/02/2020
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 01/02/2020
Type: Insulation
Result: Approved
Status: Issued
Date: 01/02/2020
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 02/05/2020
Type: Gas Test
Result: Approved
Status: Issued
Date: 02/05/2020
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 02/27/2020
Type: Service/Power Release
Result: Insp Cancelled
Status: Issued
Date: 02/27/2020
Type: ELECTRICAL-Final
Result: Insp Cancelled
Status: Issued
Date: 02/28/2020
Type: PLUMBING-Final
Result: Insp Scheduled
Status: Issued
Date: 03/04/2020
Type: Service/Power Release
Result: Not Ready for Inspection
Status: Issued
Date: 03/03/2020
Type: HVAC-Final
Result: Approved
Status: Issued
Date: 03/04/2020
Type: ELECTRICAL-Final
Result: Corrections Issued
Status: Issued
Date: 03/20/2020
Type: Green Building Final
Result: Cancelled
Status: Issued
Date: 03/20/2020
Type: Smoke Detectors
Result: Cancelled
Status: Issued
Date: 03/20/2020
Type: ELECTRICAL-Final
Result: Cancelled
Status: Issued
Date: 03/20/2020
Type: Footing/Foundation/Slab
Result: Cancelled
Status: Issued
Date: 03/20/2020
Type: Final
Result: Cancelled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
T J C HOME BUILDERS LLC

License number: 1025507
Type: B
Phone: Speak with a Permit Expert
Location: ALISO VIEJO, CA

Permit Applicant

Principal: MICHAEL ROBERT SELVIDGE
Type:
Address:
Phone:
Experience: years
Applicant: CHANTILLY BROWN