Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

New single family dwelling with attached garage in BHO. Fire sprinkle

Inspection Activity
Date: 12/21/2022
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 12/20/2022
Type: Piling/Pier/Caisson
Result: Not Ready for Inspection
Status: Issued
Date: 12/22/2022
Type: Public Counter
Result: Completed
Status: Issued
Date: 12/23/2022
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/21/2022
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 04/10/2023
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 04/10/2023
Type: ELECTRICAL-Rough
Result: Partial Approval
Status: Issued
Date: 04/11/2023
Type: Piling/Pier/Caisson
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Conditional Approval
Status: Issued
Date: 10/07/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 12/02/2022
Type: Public Counter
Result: Completed
Status: Issued
Date: 12/01/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/05/2022
Type: Piling/Pier/Caisson
Result: Partial Approval
Status: Issued
Date: 12/05/2022
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 12/05/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/26/2023
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 09/26/2023
Type: PLUMBING-Rough
Result: Approved
Status: Issued
Date: 09/26/2023
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 09/26/2023
Type: Gas Test
Result: Approved
Status: Issued
Date: 10/04/2023
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 10/04/2023
Type: BUILDING-Rough-Frame
Result: Approved
Status: Issued
Date: 10/02/2023
Type: Verify Sprinkler Sign Off
Result: Approved
Status: Issued
Date: 10/02/2023
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 10/02/2023
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/13/2023
Type: Insulation
Result: Approved
Status: Issued
Date: 10/20/2023
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 10/16/2023
Type: Interior/Exterior Lathing
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/02/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/07/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/07/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/06/2023
Type: Public Counter
Result: Completed
Status: Issued
Date: 06/06/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/06/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/07/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/20/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/23/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 06/27/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 07/24/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Corrections Issued
Status: Issued
Date: 07/28/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 08/01/2023
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 08/08/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Approved
Status: Issued
Date: 08/08/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/09/2023
Type: Public Counter
Result: Completed
Status: Issued
Date: 06/20/2024
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 09/05/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/03/2024
Type: Sewer
Result: Approved
Status: Issued
Date: 01/31/2024
Type: Drywall Nailing
Result: Cancelled
Status: Issued
Date: 02/01/2024
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/31/2024
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 01/31/2024
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
OAKHILL CONSTRUCTION INC

License number: 1013979
Type: B
Phone: Speak with a Permit Expert
Location: CALABASAS, CA

Permit Applicant

Principal: BENJAMIN PHILLIP SALISBURY

Type:

Address:

Phone:

Experience: years

Applicant: MARSHALL BELL