Bldg-Alter/Repair Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

(NDC-1084), retrofit existing building per the NDC Ordinance. 1st Floo

Inspection Activity
Date: 03/02/2022
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 03/04/2022
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 03/03/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 02/28/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 03/01/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 03/01/2022
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 12/01/2021
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/03/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 03/04/2022
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 03/01/2022
Type: METHANE-Rough
Result: Approved
Status: Issued
Date: 03/01/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 03/01/2022
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 02/28/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/10/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/10/2022
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 06/07/2022
Type: Reinforced Concrete Frame
Result: Approved
Status: Issued
Date: 06/10/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 06/08/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/09/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 06/07/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/08/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/09/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 06/07/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/10/2022
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 03/09/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/11/2022
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 03/11/2022
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 03/11/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 12/22/2021
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 03/10/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/10/2022
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 06/08/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 10/25/2021
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 03/14/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 03/16/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/15/2022
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 03/18/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/17/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/15/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 01/18/2022
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 01/19/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/20/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/19/2022
Type: Reinforced Concrete Frame
Result: Conditional Approval
Status: Issued
Date: 01/20/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 01/19/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 01/19/2022
Type: Green Building Rough
Result: Conditional Approval
Status: Issued
Date: 01/19/2022
Type: METHANE-Rough
Result: Order to Comply Issued
Status: Issued
Date: 06/14/2022
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/25/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/26/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/28/2022
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 01/27/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/24/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 01/28/2022
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 03/23/2022
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 03/24/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 03/23/2022
Type: Green Building Rough
Result: Insp Cancelled
Status: Issued
Date: 03/23/2022
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 03/25/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/02/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/01/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/04/2022
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 02/01/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/04/2022
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 02/03/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/04/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 02/04/2022
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 02/04/2022
Type: Reinforced Concrete Frame
Result: Insp Scheduled
Status: Issued
Date: 02/01/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/04/2022
Type: METHANE-Rough
Result: Insp Scheduled
Status: Issued
Date: 02/03/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/04/2022
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 02/02/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/03/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/02/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 03/24/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 03/24/2022
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 02/08/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/11/2022
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 02/11/2022
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 02/09/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/07/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/08/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/09/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/07/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 03/31/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 03/30/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/18/2022
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/17/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/15/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/18/2022
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 02/16/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/18/2022
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 02/18/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/17/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/15/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 02/16/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/18/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/01/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 02/24/2022
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/24/2022
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 02/24/2022
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 02/24/2022
Type: Deputy Reinf. Concrete
Result: Approved
Status: Issued
Date: 02/25/2022
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 02/22/2022
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 02/23/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 02/23/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/25/2022
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 06/23/2022
Type: Light Gage Steel Frame
Result: Conditional Approval
Status: Issued
Date: 04/08/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 04/04/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/06/2022
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/08/2022
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 04/07/2022
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 04/06/2022
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/15/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/14/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/12/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/13/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/15/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/13/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/14/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/15/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 04/14/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/13/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 06/28/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/29/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/22/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/21/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/20/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/20/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/22/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/21/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/20/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/20/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 06/30/2022
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 07/01/2022
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 06/29/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/30/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 06/30/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 06/27/2022
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 07/01/2022
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 06/28/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/28/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 04/27/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/25/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/26/2022
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/26/2022
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/29/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 04/28/2022
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 04/29/2022
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 04/27/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/25/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 04/26/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 07/06/2022
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/09/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/10/2022
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/12/2022
Type: Deputy Shotcrete
Result: Partial Approval
Status: Issued
Date: 05/11/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/13/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 05/10/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 09/13/2022
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 09/14/2022
Type: AIM Verification
Result: Not Applicable
Status: Issued
Date: 09/13/2022
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 09/13/2022
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 09/13/2022
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/19/2022
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/19/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 05/20/2022
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/20/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 05/18/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/17/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/27/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/26/2022
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/25/2022
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/24/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/26/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 05/27/2022
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/23/2022
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 05/23/2022
Type: Deputy Shotcrete
Result: Insp Scheduled
Status: Issued
Date: 05/25/2022
Type: Deputy Shotcrete
Result: Conditional Approval
Status: Issued
Date: 09/13/2022
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 05/31/2022
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 06/02/2022
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 07/21/2022
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/18/2022
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 07/21/2022
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 07/18/2022
Type: Drywall Nailing
Result: Conditional Approval
Status: Issued
Date: 07/27/2022
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 08/05/2022
Type: Drywall Nailing
Result: Insp Scheduled
Status: Issued
Date: 08/11/2022
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 08/11/2022
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 08/04/2023
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 08/03/2023
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 08/03/2023
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 08/04/2023
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 08/09/2023
Type: Electrical Verification
Result: CofO on Hold
Status: Issued
Date: 08/07/2023
Type: Heat,Vent,A/C Verification
Result: CofO on Hold
Status: Issued
Date: 08/08/2023
Type: Green Building Final
Result: Approved
Status: Issued
Date: 08/08/2023
Type: Final
Result: Partial Approval
Status: Issued
Date: 08/08/2023
Type: Elevator Verification
Result: OK for CofO
Status: Issued
Date: 08/07/2023
Type: Plumbing Verification
Result: OK for CofO
Status: Issued
Date: 08/14/2023
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 08/14/2023
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Date: 08/14/2023
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 08/14/2023
Type: Inspection
Result: OK for CofO
Status: CofO Issued
Date: 08/14/2023
Type: CofO Issuance
Result: CofO in Progress
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
HOPKINS GEORGE C CONSTRUCTION CO INC

License number: 397266
Type: B
Phone: Speak with a Permit Expert
Location: GLENDALE, CA

Permit Applicant

Principal: GARY JOSEPH HOPKINS

Type:

Address:

Phone:

Experience: years

Applicant: TOM MAJICH