Bldg-New Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

NEW FOUR TIER PARKING STRUCTURE

Inspection Activity
Date: 09/27/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 09/27/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/26/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/28/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Cancelled
Status: Issued
Date: 09/29/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/03/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 10/04/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 10/06/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 10/05/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/05/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 10/13/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/12/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/11/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/11/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 05/17/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2023
Type: METHANE-Subgrade
Result: Partial Inspection
Status: Issued
Date: 05/16/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/16/2023
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 05/16/2023
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 05/19/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/18/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/17/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/16/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 10/17/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 05/25/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 05/24/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/24/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 05/26/2023
Type: Pre-Inspection
Result: Insp Cancelled
Status: Issued
Date: 05/24/2023
Type: METHANE-Subgrade
Result: Not Ready for Inspection
Status: Issued
Date: 05/26/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 05/24/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 05/24/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 05/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 05/23/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/20/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/18/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/20/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/18/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/01/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/01/2023
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2023
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 06/01/2023
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/23/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/06/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/08/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 10/26/2023
Type: METHANE-Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/27/2023
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 10/24/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/26/2023
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 10/26/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 10/26/2023
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 10/27/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 10/24/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 06/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 06/20/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 06/23/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 06/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 11/03/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/03/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/02/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/30/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 10/30/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 10/31/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 11/02/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 10/31/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 11/01/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/06/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/06/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/09/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 11/08/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 11/06/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/09/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 11/07/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 07/17/2023
Type: METHANE-Subgrade
Result: Partial Approval
Status: Issued
Date: 11/16/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 07/28/2023
Type: METHANE-Subgrade
Result: Approved
Status: Issued
Date: 07/28/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 07/28/2023
Type: METHANE-Barrier
Result: Partial Inspection
Status: Issued
Date: 07/29/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 11/17/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 11/15/2023
Type: Deputy Reinf. Concrete
Result: Partial Approval
Status: Issued
Date: 11/13/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 11/15/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 07/31/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/31/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/07/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 08/07/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/08/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 08/07/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/16/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 08/18/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/17/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 06/17/2024
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 11/27/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/29/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 08/23/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Inspection
Status: Issued
Date: 08/22/2023
Type: Reinforced Concrete Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/23/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/24/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 08/25/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/23/2023
Type: METHANE-Barrier
Result: Not Ready for Inspection
Status: Issued
Date: 11/28/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 11/30/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 11/29/2023
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 11/30/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 08/31/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 08/28/2023
Type: Deputy Pre-Stress Concrete
Result: Approved
Status: Issued
Date: 08/31/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/30/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/30/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/28/2023
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 09/07/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/08/2023
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 09/06/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/07/2023
Type: Deputy Pre-Stress Concrete
Result: Partial Approval
Status: Issued
Date: 12/08/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/04/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 12/07/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/06/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 12/05/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/08/2023
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 12/07/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/06/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 09/12/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/13/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/12/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/21/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 09/18/2023
Type: Deputy Other (see comments)
Result: Approved
Status: Issued
Date: 09/18/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 09/19/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 09/22/2023
Type: Deputy Pre-Stress Concrete
Result: Insp Scheduled
Status: Issued
Date: 09/20/2023
Type: Deputy Pre-Stress Concrete
Result: Conditional Approval
Status: Issued
Date: 12/14/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/13/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/11/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 12/14/2023
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 12/15/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/12/2023
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 12/11/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/12/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 12/18/2023
Type: Masonry Wall/Backfill
Result: Partial Approval
Status: Issued
Date: 12/18/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 12/18/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 12/22/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 12/19/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 12/21/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 12/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 12/27/2023
Type: Public Counter
Result: Completed
Status: Issued
Date: 12/29/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 12/26/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/04/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/02/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/05/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/09/2024
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 01/12/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 01/11/2024
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 01/08/2024
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 02/20/2024
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 02/22/2024
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 02/21/2024
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 02/29/2024
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 03/05/2024
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 03/27/2024
Type: Special/Order Compliance
Result: Approved
Status: Issued
Date: 03/29/2024
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 04/01/2024
Type: METHANE-Rough
Result: Approved
Status: Issued
Date: 04/01/2024
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 04/01/2024
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV No Gas
Status: Issued
Date: 04/01/2024
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 04/01/2024
Type: METHANE-Barrier
Result: Approved
Status: Issued
Date: 04/02/2024
Type: AIM Verification
Result: Not Applicable
Status: Issued
Date: 04/01/2024
Type: METHANE-Final
Result: Not Ready for Inspection
Status: Issued
Date: 04/01/2024
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 04/01/2024
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 04/01/2024
Type: Final
Result: Corrections Issued
Status: Issued
Date: 04/01/2024
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
WEST HILLS CONSTRUCTION INC

License number: 578578
Type: B
Phone: Speak with a Permit Expert
Location: CORONA, CA

Permit Applicant

Principal: ROSS LEONARD WOOD

Type:

Address: 835 MISSION STREET, SOUTH PASADENA

Phone:

Experience: years

Applicant: SARHAD GHEVANDIAN