Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

ADD (22'-0" x 23'-6") IRR. SHAPE BEDROOM,WITH CLOSET AND FULL BATHROOM

Inspection Activity
Date: 01/17/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 01/18/2023
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 02/06/2023
Type: Green Building Rough
Result: Partial Inspection
Status: Issued
Date: 02/06/2023
Type: PLUMBING-Rough
Result: Partial Approval
Status: Issued
Date: 02/09/2023
Type: HVAC-Rough
Result: Cancelled
Status: Issued
Date: 02/06/2023
Type: Underground Mechanical
Result: Partial Inspection
Status: Issued
Date: 02/09/2023
Type: ELECTRICAL-Rough
Result: Cancelled
Status: Issued
Date: 02/09/2023
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 02/09/2023
Type: BUILDING-Rough-Frame
Result: Partial Approval
Status: Issued
Date: 02/06/2023
Type: BUILDING-Rough-Frame
Result: Corrections Issued
Status: Issued
Date: 02/09/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Approval
Status: Issued
Date: 03/31/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Insp Scheduled
Status: Issued
Date: 05/08/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/08/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/08/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/08/2023
Type: Floor/Roof Diaphrgm/Shear Wall
Result: Partial Inspection
Status: Issued
Date: 05/15/2023
Type: HVAC-Rough
Result: Approved
Status: Issued
Date: 05/15/2023
Type: ELECTRICAL-Rough
Result: Approved
Status: Issued
Date: 05/19/2023
Type: Deputy Wood Construction
Result: Insp Scheduled
Status: Issued
Date: 05/15/2023
Type: Green Building Rough
Result: Not Ready for Inspection
Status: Issued
Date: 05/15/2023
Type: BUILDING-Rough-Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/15/2023
Type: PLUMBING-Rough
Result: Corrections Issued
Status: Issued
Date: 11/01/2023
Type: Green Building Final
Result: Approved
Status: Issued
Date: 11/01/2023
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 11/01/2023
Type: Final
Result: Conditional Approval
Status: Issued
Date: 11/01/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 07/07/2023
Type: Green Building Rough
Result: Insp Scheduled
Status: Issued
Date: 07/07/2023
Type: BUILDING-Rough-Frame
Result: Insp Scheduled
Status: Issued
Date: 07/12/2023
Type: Shower Pan
Result: Approved
Status: Issued
Date: 07/12/2023
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 07/26/2023
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 03/06/2024
Type: HVAC-Final
Result: Approved
Status: CofO in Progress
Date: 03/05/2024
Type: HVAC-Final
Result: Insp Scheduled
Status: CofO in Progress
Date: 03/05/2024
Type: PLUMBING-Final
Result: Insp Scheduled
Status: CofO in Progress
Date: 03/06/2024
Type: ELECTRICAL-Final
Result: Approved
Status: CofO in Progress
Date: 03/06/2024
Type: PLUMBING-Final
Result: Approved
Status: CofO in Progress
Date: 03/06/2024
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 03/05/2024
Type: Service/Power Release
Result: Insp Scheduled
Status: CofO in Progress
Date: 03/06/2024
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 03/05/2024
Type: ELECTRICAL-Final
Result: Insp Scheduled
Status: CofO in Progress
Date: 03/05/2024
Type: Final
Result: Insp Scheduled
Status: CofO in Progress
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
ING CONSTRUCTION & INV

License number: 961589
Type: B
Phone: Speak with a Permit Expert
Location: VAN NUYS, CA

Permit Applicant

Principal: GOLAN-DAVID DANINO

Type:

Address:

Phone:

Experience: years

Applicant: ILAN DEMBSKY