Bldg-Addition Permit

Permit Type: New Construction Permit

Work Category: 1 or 2 Family Dwellin

PCIS Permit#: 22014-10000-04294

Status: Issued on 10/11/2023

Status Date: 03/04/2015

Work Description:
STE 3100 Non-Structural Interior office tile work includes non-structure includes non-structure.

Address: 12310 1st Helena, Los Angeles, 90049

Property Identifier: Block: 1, Lot: 12, Zone: RS-1

Assessor Information: Book: 7449, Page: 14, Parcel:

Geo Info:Tract: TR 5462, Census Tract: 2640

Popular Projects Nearby

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Inspection Activity 3

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
PCIS Permit#: Date:
03/04/2015
Status:
Permit Finaled
Result:
Approved
Work Description

ePLAN- 1. CHANGE USE & TENANT IMPROVEMENT: PROPOSED CHANGE OF USE FR

Inspection Activity
Date: 04/11/2023
Type: METHANE-Rough
Result: Insp Cancelled
Status: Issued
Date: 04/14/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Reinforced Masonry Frame
Result: Partial Approval
Status: Issued
Date: 04/14/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Deputy Reinf. Masonry
Result: Partial Approval
Status: Issued
Date: 04/14/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/14/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/14/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Deputy Steel/Welding
Result: Insp Cancelled
Status: Issued
Date: 04/14/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/11/2023
Type: Deputy Reinf. Masonry
Result: Insp Cancelled
Status: Issued
Date: 04/11/2023
Type: Green Building Rough
Result: Approved
Status: Issued
Date: 03/31/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Scheduled
Status: Issued
Date: 03/31/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 03/28/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 03/30/2023
Type: Deputy Steel/Welding
Result: Insp Cancelled
Status: Issued
Date: 03/31/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 04/19/2023
Type: Reinforced Concrete Frame
Result: Partial Approval
Status: Issued
Date: 04/19/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/19/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 04/24/2023
Type: Deputy Steel/Welding
Result: Insp Cancelled
Status: Issued
Date: 04/24/2023
Type: Piling/Pier/Caisson
Result: Insp Cancelled
Status: Issued
Date: 04/24/2023
Type: METHANE-Barrier
Result: Insp Cancelled
Status: Issued
Date: 04/26/2023
Type: Deputy Drilled-In Anchors
Result: Insp Cancelled
Status: Issued
Date: 04/26/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/24/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/24/2023
Type: Deputy Steel/Welding
Result: Insp Cancelled
Status: Issued
Date: 04/28/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 04/24/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/26/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/28/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Cancelled
Status: Issued
Date: 04/24/2023
Type: METHANE-Subgrade
Result: Insp Cancelled
Status: Issued
Date: 04/24/2023
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 04/24/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Insp Cancelled
Status: Issued
Date: 04/28/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 04/24/2023
Type: Reinforced Concrete Frame
Result: Insp Cancelled
Status: Issued
Date: 04/24/2023
Type: Footing/Foundation/Slab
Result: Corrections Issued
Status: Issued
Date: 04/26/2023
Type: Deputy Steel/Welding
Result: Insp Cancelled
Status: Issued
Date: 05/03/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/03/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 05/05/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/05/2023
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 05/05/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/02/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 05/02/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/05/2023
Type: Pre-Inspection
Result: Insp Scheduled
Status: Issued
Date: 05/03/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/01/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/04/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/02/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/05/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/04/2023
Type: Deputy Reinf. Masonry
Result: Conditional Approval
Status: Issued
Date: 05/04/2023
Type: Deputy Drilled-In Anchors
Result: Conditional Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/10/2023
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/09/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/10/2023
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/09/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/10/2023
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/09/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 05/10/2023
Type: Structural Steel Frame
Result: Conditional Approval
Status: Issued
Date: 05/09/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/19/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/19/2023
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 05/22/2023
Type: Insulation
Result: Approved
Status: Issued
Date: 05/25/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 05/23/2023
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 05/25/2023
Type: Deputy Steel/Welding
Result: Approved
Status: Issued
Date: 05/23/2023
Type: Masonry Wall/Backfill
Result: Not Ready for Inspection
Status: Issued
Date: 05/26/2023
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 05/26/2023
Type: Masonry Wall/Backfill
Result: Insp Scheduled
Status: Issued
Date: 05/26/2023
Type: Light Gage Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 05/25/2023
Type: Deputy Reinf. Masonry
Result: Approved
Status: Issued
Date: 05/22/2023
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 05/25/2023
Type: Masonry Wall/Backfill
Result: Approved
Status: Issued
Date: 05/26/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 05/26/2023
Type: Deputy Reinf. Masonry
Result: Insp Scheduled
Status: Issued
Date: 05/31/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 06/01/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/30/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/31/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/02/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 05/30/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/31/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 06/01/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 05/31/2023
Type: Light Gage Steel Frame
Result: Approved
Status: Issued
Date: 05/31/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/02/2023
Type: Structural Steel Frame
Result: Insp Scheduled
Status: Issued
Date: 05/31/2023
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/02/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/05/2023
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 06/08/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/07/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 06/08/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/06/2023
Type: Drywall Nailing
Result: Not Ready for Inspection
Status: Issued
Date: 06/06/2023
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/08/2023
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Date: 06/06/2023
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Date: 06/06/2023
Type: Insulation
Result: Insp Cancelled
Status: Issued
Date: 06/09/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 06/05/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/08/2023
Type: Light Gage Steel Frame
Result: Insp Cancelled
Status: Issued
Date: 06/08/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 06/12/2023
Type: Masonry Wall/Backfill
Result: Partial Inspection
Status: Issued
Date: 06/13/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 06/13/2023
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 06/16/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/22/2023
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 06/21/2023
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/21/2023
Type: Light Gage Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 06/29/2023
Type: Insulation
Result: Insp Cancelled
Status: Issued
Date: 06/28/2023
Type: Insulation
Result: Approved
Status: Issued
Date: 06/27/2023
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 06/29/2023
Type: Light Gage Steel Frame
Result: Approved
Status: Issued
Date: 06/29/2023
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 06/27/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 06/27/2023
Type: Structural Steel Frame
Result: Insp Cancelled
Status: Issued
Date: 06/30/2023
Type: Light Gage Steel Frame
Result: Approved
Status: Issued
Date: 06/30/2023
Type: Insulation
Result: Approved
Status: Issued
Date: 07/06/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/07/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/03/2023
Type: Drywall Nailing
Result: Cancelled
Status: Issued
Date: 07/06/2023
Type: Insulation
Result: Partial Approval
Status: Issued
Date: 07/03/2023
Type: Light Gage Steel Frame
Result: Cancelled
Status: Issued
Date: 07/06/2023
Type: Masonry Wall/Backfill
Result: Approved
Status: Issued
Date: 07/10/2023
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 07/11/2023
Type: Deputy Drilled-In Anchors
Result: Insp Scheduled
Status: Issued
Date: 07/11/2023
Type: Interior/Exterior Lathing
Result: Approved
Status: Issued
Date: 07/13/2023
Type: Drywall Nailing
Result: Partial Approval
Status: Issued
Date: 07/11/2023
Type: Drywall Nailing
Result: Approved
Status: Issued
Date: 07/13/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/11/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 07/11/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 07/12/2023
Type: Light Gage Steel Frame
Result: Approved
Status: Issued
Date: 07/20/2023
Type: Piling/Pier/Caisson
Result: Cancelled
Status: Issued
Date: 07/19/2023
Type: Piling/Pier/Caisson
Result: Corrections Issued
Status: Issued
Date: 07/19/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 07/17/2023
Type: Pre-Inspection
Result: Partial Inspection
Status: Issued
Date: 07/17/2023
Type: Special/Order Compliance
Result: Partial Inspection
Status: Issued
Date: 07/25/2023
Type: Footing/Foundation/Slab
Result: Partial Inspection
Status: Issued
Date: 07/27/2023
Type: Footing/Foundation/Slab
Result: Partial Approval
Status: Issued
Date: 08/01/2023
Type: Deputy Reinf. Concrete
Result: Insp Scheduled
Status: Issued
Date: 08/02/2023
Type: T-Bar Ceiling
Result: Not Ready for Inspection
Status: Issued
Date: 08/08/2023
Type: T-Bar Ceiling
Result: Not Ready for Inspection
Status: Issued
Date: 08/10/2023
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 08/07/2023
Type: T-Bar Ceiling
Result: Not Ready for Inspection
Status: Issued
Date: 08/11/2023
Type: Deputy Fireproofing
Result: Insp Scheduled
Status: Issued
Date: 08/09/2023
Type: Deputy Fireproofing
Result: Conditional Approval
Status: Issued
Date: 08/10/2023
Type: T-Bar Ceiling
Result: Insp Scheduled
Status: Issued
Date: 08/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Partial Approval
Status: Issued
Date: 08/16/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Off-Hour Fees Due
Status: Issued
Date: 08/14/2023
Type: Deputy Steel/Welding
Result: Insp Scheduled
Status: Issued
Date: 08/16/2023
Type: Deputy Reinf. Concrete
Result: Conditional Approval
Status: Issued
Date: 08/15/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 08/16/2023
Type: Structural Steel Frame
Result: Off-Hour Fees Due
Status: Issued
Date: 08/17/2023
Type: Light Gage Steel Frame
Result: Partial Approval
Status: Issued
Date: 08/15/2023
Type: Structural Steel Frame
Result: Not Ready for Inspection
Status: Issued
Date: 08/16/2023
Type: Deputy Steel/Welding
Result: Conditional Approval
Status: Issued
Date: 08/14/2023
Type: Structural Steel Frame
Result: Cancelled
Status: Issued
Date: 08/16/2023
Type: Structural Steel Frame
Result: Partial Approval
Status: Issued
Date: 08/21/2023
Type: Excavation/Setback/Form/Re-Bar
Result: Not Ready for Inspection
Status: Issued
Date: 08/21/2023
Type: Structural Steel Frame
Result: Partial Inspection
Status: Issued
Date: 09/01/2023
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: METHANE-Final
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 09/01/2023
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 09/11/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 09/11/2023
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 09/15/2023
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 09/14/2023
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 09/11/2023
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/14/2023
Type: Final
Result: Cancelled
Status: Issued
Date: 09/14/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 09/11/2023
Type: Smoke Detectors
Result: Not Ready for Inspection
Status: Issued
Date: 09/14/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 09/11/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Not Ready
Status: Issued
Date: 09/14/2023
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 09/14/2023
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 09/11/2023
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/11/2023
Type: METHANE-Final
Result: Not Ready for Inspection
Status: Issued
Date: 09/14/2023
Type: METHANE-Final
Result: Insp Cancelled
Status: Issued
Date: 12/15/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 09/19/2023
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 09/19/2023
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 09/19/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Cancelled
Status: Issued
Date: 09/22/2023
Type: Special/Order Compliance
Result: Insp Scheduled
Status: Issued
Date: 09/19/2023
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 09/19/2023
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 09/22/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 09/22/2023
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 09/22/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Scheduled
Status: Issued
Date: 09/22/2023
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 09/22/2023
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 09/19/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 12/15/2023
Type: Smoke Detectors
Result: Insp Scheduled
Status: Issued
Date: 12/15/2023
Type: Footing/Foundation/Slab
Result: Insp Scheduled
Status: Issued
Date: 12/15/2023
Type: Final
Result: Insp Scheduled
Status: Issued
Date: 12/15/2023
Type: Green Building Final
Result: Insp Scheduled
Status: Issued
Date: 12/15/2023
Type: Reinforced Masonry Frame
Result: Insp Scheduled
Status: Issued
Date: 12/21/2023
Type: Green Building Final
Result: Insp Cancelled
Status: Issued
Date: 12/22/2023
Type: Reinforced Masonry Frame
Result: Not Ready for Inspection
Status: Issued
Date: 12/22/2023
Type: Green Building Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/22/2023
Type: Smoke Detectors
Result: Approved
Status: Issued
Date: 12/22/2023
Type: Final
Result: Not Ready for Inspection
Status: Issued
Date: 12/21/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: Insp Cancelled
Status: Issued
Date: 12/21/2023
Type: Smoke Detectors
Result: Insp Cancelled
Status: Issued
Date: 12/22/2023
Type: SGSOV-Seismic Gas S/O Valve
Result: SGSOV Approved
Status: Issued
Date: 12/21/2023
Type: Reinforced Masonry Frame
Result: Insp Cancelled
Status: Issued
Date: 12/21/2023
Type: Final
Result: Insp Cancelled
Status: Issued
Date: 12/22/2023
Type: Footing/Foundation/Slab
Result: Not Ready for Inspection
Status: Issued
Date: 12/21/2023
Type: Footing/Foundation/Slab
Result: Insp Cancelled
Status: Issued
Date: 01/04/2024
Type: Footing/Foundation/Slab
Result: Approved
Status: Issued
Date: 01/04/2024
Type: Final
Result: Partial Inspection
Status: Issued
Date: 01/04/2024
Type: Reinforced Masonry Frame
Result: Approved
Status: Issued
Date: 01/04/2024
Type: Green Building Final
Result: Approved
Status: Issued
Date: 01/12/2024
Type: CofO Issuance
Result: CofO in Progress
Status: CofO in Progress
Date: 01/12/2024
Type: Final
Result: OK to Issue CofO
Status: CofO in Progress
Date: 01/11/2024
Type: Plumbing Verification
Result: OK for CofO
Status: CofO in Progress
Date: 01/10/2024
Type: Final
Result: Insp Cancelled
Status: CofO in Progress
Date: 01/11/2024
Type: Heat,Vent,A/C Verification
Result: OK for CofO
Status: CofO in Progress
Date: 01/11/2024
Type: Electrical Verification
Result: OK for CofO
Status: CofO in Progress
Date: 01/16/2024
Type: Elevator Verification
Result: OK for CofO
Status: CofO Issued
Date: 01/19/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/19/2024
Type: Inspection
Result: Permit Finaled
Status: CofO Issued
Date: 01/19/2024
Type: CofO Issuance
Result: CofO Issued
Status: CofO Issued
Permit Expediting Services

Fast-track your permit approval process with our specialized expediting services tailored to your needs.

Request a Quote

Ready to get started? Get a personalized estimate for your project.

Get Your Quote
Contractor Info
BERGMAN KPRS LLC

License number: 982577
Type: B
Phone: Speak with a Permit Expert
Location: BREA, CA

Permit Applicant

Principal: MARK CURTIS BERGMAN

Type:

Address: 18872 Mc Arthur, Irvine

Phone:

Experience: years

Applicant: ZAHRA KHARRAZI